🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Michael can finish the work in 30 days and Thomas can finish the same work in 46 days, then in how many days both can finish the work together?


Correct Answer  18 3/19 days or 18.158 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Michael = 30 days

And, the number of days to finish the same work by Thomas = 46 days

Thus, the number of days to finish the work by Michael and Thomas together = ?

Here,

∵ In 30 days the work done by Michael = 1

∴ In 1 day, the work done by Michael = 1/30 part

Similarly,

∵ In 46 days the work done by Thomas = 1

∴ In 1 day, the work done by Thomas = 1/46 part

Now, in 1 day, the work done by Michael and Thomas together

= In 1 day work done by Michael + In 1 day the work done by Thomas

= 1/30 + 1/46

= 23 + 15/690

= 38/690 part of work

= 38 ÷ 2/690 ÷ 2 part of work

= 19/345 part of work

This means, in 1 day, 19/345 part of the work is done by Michael and Thomas together.

Now, the number of days required to finish 19/345 part of work by Michael + Thomas working together = 1

∴ the number of days required to finish 1 work by Michael + Thomas together

= 1/19/345

= 1 × 345/19 = 345/19 days

= 18 3/19 days = or 18.158 days

Thus, Michael and Thomas working together will finish the work in 18 3/19 days = or 18.158 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Michael = 30 days

And the number of days required to finish the same work by Thomas = 46 days

Thus, the number of days required to finish the work Michael and Thomas working together = ?

Here a = 30 days

And, b = 46 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Michael and Thomas working together

= 30 × 46/30 + 46 days

= 1380/76 days

= 1380 ÷ 4/76 ÷ 4 = 345/19 days

= 18 3/19 days or 18.158

Thus, Michael and Thomas together will finish the work in 18 3/19 days or 18.158 days Answer


Similar Questions

(1) If George can finish the work in 51 days and Dennis can finish the same work in 56 days, then in how many days both can finish the work together?

(2) Carol can finish a work in 46 days. Dorothy can finish the same work in 51 days while Melissa can finish the work in 56 days. How long will it take to finish it if they work together?

(3) If Catherine can finish the work in 100 days and Mason can finish the same work in 105 days, then in how many days both can finish the work together?

(4) If Jonathan can finish the work in 73 days and Sean can finish the same work in 78 days, then in how many days both can finish the work together?

(5) If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?

(6) Mark can finish a work in 33 days. Steven can finish the same work in 38 days while Paul can finish the work in 43 days. How long will it take to finish it if they work together?

(7) If Kimberly can finish the work in 38 days and Stephen can finish the same work in 43 days, then in how many days both can finish the work together?

(8) If Christopher can finish the work in 22 days and Brian can finish the same work in 26 days, then in how many days both can finish the work together?

(9) If John can finish the work in 6 days and Richard can finish the same work in 9 days, then in how many days both can finish the work together?

(10) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?