🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If James can finish the work in 2 days and John can finish the same work in 6 days, then in how many days both can finish the work together?


Correct Answer  1 1/2 days or 1.5 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by James = 2 days

And, the number of days to finish the same work by John = 6 days

Thus, the number of days to finish the work by James and John together = ?

Here,

∵ In 2 days the work done by James = 1

∴ In 1 day, the work done by James = 1/2 part

Similarly,

∵ In 6 days the work done by John = 1

∴ In 1 day, the work done by John = 1/6 part

Now, in 1 day, the work done by James and John together

= In 1 day work done by James + In 1 day the work done by John

= 1/2 + 1/6

= 3 + 1/6

= 4/6 part of work

= 4 ÷ 2/6 ÷ 2 part of work

= 2/3 part of work

This means, in 1 day, 2/3 part of the work is done by James and John together.

Now, the number of days required to finish 2/3 part of work by James + John working together = 1

∴ the number of days required to finish 1 work by James + John together

= 1/2/3

= 1 × 3/2 = 3/2 days

= 1 1/2 days = or 1.5 days

Thus, James and John working together will finish the work in 1 1/2 days = or 1.5 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by James = 2 days

And the number of days required to finish the same work by John = 6 days

Thus, the number of days required to finish the work James and John working together = ?

Here a = 2 days

And, b = 6 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when James and John working together

= 2 × 6/2 + 6 days

= 12/8 days

= 12 ÷ 4/8 ÷ 4 = 3/2 days

= 1 1/2 days or 1.5

Thus, James and John together will finish the work in 1 1/2 days or 1.5 days Answer


Similar Questions

(1) If Kimberly can finish the work in 38 days and Stephen can finish the same work in 43 days, then in how many days both can finish the work together?

(2) Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?

(3) If Donald can finish the work in 35 days and Nicholas can finish the same work in 40 days, then in how many days both can finish the work together?

(4) If Andrew can finish the work in 41 days and Scott can finish the same work in 46 days, then in how many days both can finish the work together?

(5) If Michelle can finish the work in 41 days and Samuel can finish the same work in 44 days, then in how many days both can finish the work together?

(6) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(7) If Nancy can finish the work in 28 days and Ronald can finish the same work in 33 days, then in how many days both can finish the work together?

(8) John can finish a work in 9 days. David can finish the same work in 14 days while William can finish the work in 19 days. How long will it take to finish it if they work together?

(9) If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 14 days, then in how many days both can finish the work together?

(10) If Christopher can finish the work in 22 days and Brian can finish the same work in 26 days, then in how many days both can finish the work together?