🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If John can finish the work in 6 days and Richard can finish the same work in 10 days, then in how many days both can finish the work together?


Correct Answer  3 3/4 days or 3.75 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by John = 6 days

And, the number of days to finish the same work by Richard = 10 days

Thus, the number of days to finish the work by John and Richard together = ?

Here,

∵ In 6 days the work done by John = 1

∴ In 1 day, the work done by John = 1/6 part

Similarly,

∵ In 10 days the work done by Richard = 1

∴ In 1 day, the work done by Richard = 1/10 part

Now, in 1 day, the work done by John and Richard together

= In 1 day work done by John + In 1 day the work done by Richard

= 1/6 + 1/10

= 5 + 3/30

= 8/30 part of work

= 8 ÷ 2/30 ÷ 2 part of work

= 4/15 part of work

This means, in 1 day, 4/15 part of the work is done by John and Richard together.

Now, the number of days required to finish 4/15 part of work by John + Richard working together = 1

∴ the number of days required to finish 1 work by John + Richard together

= 1/4/15

= 1 × 15/4 = 15/4 days

= 3 3/4 days = or 3.75 days

Thus, John and Richard working together will finish the work in 3 3/4 days = or 3.75 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by John = 6 days

And the number of days required to finish the same work by Richard = 10 days

Thus, the number of days required to finish the work John and Richard working together = ?

Here a = 6 days

And, b = 10 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when John and Richard working together

= 6 × 10/6 + 10 days

= 60/16 days

= 60 ÷ 4/16 ÷ 4 = 15/4 days

= 3 3/4 days or 3.75

Thus, John and Richard together will finish the work in 3 3/4 days or 3.75 days Answer


Similar Questions

(1) Gary can finish a work in 67 days. Eric can finish the same work in 72 days while Jonathan can finish the work in 77 days. How long will it take to finish it if they work together?

(2) Larry can finish a work in 77 days. Scott can finish the same work in 82 days while Brandon can finish the work in 87 days. How long will it take to finish it if they work together?

(3) If Margaret can finish the work in 29 days and Ryan can finish the same work in 33 days, then in how many days both can finish the work together?

(4) If Carol can finish the work in 43 days and Alexander can finish the same work in 47 days, then in how many days both can finish the work together?

(5) If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?

(6) Catherine can finish a work in 100 days. Heather can finish the same work in 105 days while Diane can finish the work in 110 days. How long will it take to finish it if they work together?

(7) Angela can finish a work in 70 days. Anna can finish the same work in 75 days while Brenda can finish the work in 80 days. How long will it take to finish it if they work together?

(8) Emily can finish a work in 40 days. Michelle can finish the same work in 45 days while Carol can finish the work in 50 days. How long will it take to finish it if they work together?

(9) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?

(10) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?