🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If William can finish the work in 12 days and Matthew can finish the same work in 16 days, then in how many days both can finish the work together?


Correct Answer  6 6/7 days or 6.857 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by William = 12 days

And, the number of days to finish the same work by Matthew = 16 days

Thus, the number of days to finish the work by William and Matthew together = ?

Here,

∵ In 12 days the work done by William = 1

∴ In 1 day, the work done by William = 1/12 part

Similarly,

∵ In 16 days the work done by Matthew = 1

∴ In 1 day, the work done by Matthew = 1/16 part

Now, in 1 day, the work done by William and Matthew together

= In 1 day work done by William + In 1 day the work done by Matthew

= 1/12 + 1/16

= 4 + 3/48

= 7/48 part of work

This means in 1 day, 7/48 part of work is done by William and Matthew working together.

Now, the number of days required to finish 7/48 part of work by William + Matthew working together = 1

∴ the number of days required to finish 1 work by William + Matthew together

= 1/7/48

= 1 × 48/7 = 48/7 days

= 6 6/7 days = or 6.857 days

Thus, William and Matthew working together will finish the work in 6 6/7 days = or 6.857 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by William = 12 days

And the number of days required to finish the same work by Matthew = 16 days

Thus, the number of days required to finish the work William and Matthew working together = ?

Here a = 12 days

And, b = 16 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when William and Matthew working together

= 12 × 16/12 + 16 days

= 192/28 days

= 192 ÷ 4/28 ÷ 4 = 48/7 days

= 6 6/7 days or 6.857

Thus, William and Matthew together will finish the work in 6 6/7 days or 6.857 days Answer


Similar Questions

(1) Patricia can finish a work in 4 days. Jennifer can finish the same work in 5 days while Linda can finish the work in 6 days. How long will it take to finish it if they work together?

(2) Thomas can finish a work in 17 days. Charles can finish the same work in 18 days while Christopher can finish the work in 19 days. How long will it take to finish it if they work together?

(3) If Donald can finish the work in 35 days and Nicholas can finish the same work in 40 days, then in how many days both can finish the work together?

(4) Carolyn can finish a work in 96 days. Catherine can finish the same work in 101 days while Maria can finish the work in 106 days. How long will it take to finish it if they work together?

(5) Carol can finish a work in 46 days. Dorothy can finish the same work in 51 days while Melissa can finish the work in 56 days. How long will it take to finish it if they work together?

(6) If A can finish a work in 10 days and B can finish the same work in 15 days, then in how many days they both can finish the work working together?

(7) If Lisa can finish the work in 23 days and George can finish the same work in 27 days, then in how many days both can finish the work together?

(8) Karen can finish a work in 20 days. Lisa can finish the same work in 21 days while Nancy can finish the work in 22 days. How long will it take to finish it if they work together?

(9) Michael can finish a work in 7 days. David can finish the same work in 8 days while William can finish the work in 9 days. How long will it take to finish it if they work together?

(10) If Michelle can finish the work in 41 days and Samuel can finish the same work in 45 days, then in how many days both can finish the work together?