🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Sarah can finish the work in 19 days and Joshua can finish the same work in 23 days, then in how many days both can finish the work together?


Correct Answer  10 17/42 days or 10.405 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Sarah = 19 days

And, the number of days to finish the same work by Joshua = 23 days

Thus, the number of days to finish the work by Sarah and Joshua together = ?

Here,

∵ In 19 days the work done by Sarah = 1

∴ In 1 day, the work done by Sarah = 1/19 part

Similarly,

∵ In 23 days the work done by Joshua = 1

∴ In 1 day, the work done by Joshua = 1/23 part

Now, in 1 day, the work done by Sarah and Joshua together

= In 1 day work done by Sarah + In 1 day the work done by Joshua

= 1/19 + 1/23

= 23 + 19/437

= 42/437 part of work

This means in 1 day, 42/437 part of work is done by Sarah and Joshua working together.

Now, the number of days required to finish 42/437 part of work by Sarah + Joshua working together = 1

∴ the number of days required to finish 1 work by Sarah + Joshua together

= 1/42/437

= 1 × 437/42 = 437/42 days

= 10 17/42 days = or 10.405 days

Thus, Sarah and Joshua working together will finish the work in 10 17/42 days = or 10.405 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Sarah = 19 days

And the number of days required to finish the same work by Joshua = 23 days

Thus, the number of days required to finish the work Sarah and Joshua working together = ?

Here a = 19 days

And, b = 23 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Sarah and Joshua working together

= 19 × 23/19 + 23 days

= 437/42 days

= 10 17/42 days or 10.405

Thus, Sarah and Joshua together will finish the work in 10 17/42 days or 10.405 days Answer


Similar Questions

(1) If Charles can finish the work in 20 days and Kenneth can finish the same work in 24 days, then in how many days both can finish the work together?

(2) If Brian can finish the work in 46 days and Raymond can finish the same work in 49 days, then in how many days both can finish the work together?

(3) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(4) Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?

(5) If Brandon can finish the work in 83 days and Joe can finish the same work in 88 days, then in how many days both can finish the work together?

(6) If Laura can finish the work in 62 days and Kyle can finish the same work in 67 days, then in how many days both can finish the work together?

(7) If George can finish the work in 48 days and Dennis can finish the same work in 51 days, then in how many days both can finish the work together?

(8) If Christine can finish the work in 90 days and Juan can finish the same work in 95 days, then in how many days both can finish the work together?

(9) If Charles can finish the work in 23 days and Kenneth can finish the same work in 28 days, then in how many days both can finish the work together?

(10) Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?