🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Kimberly can finish the work in 35 days and Stephen can finish the same work in 39 days, then in how many days both can finish the work together?


Correct Answer  18 33/74 days or 18.446 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Kimberly = 35 days

And, the number of days to finish the same work by Stephen = 39 days

Thus, the number of days to finish the work by Kimberly and Stephen together = ?

Here,

∵ In 35 days the work done by Kimberly = 1

∴ In 1 day, the work done by Kimberly = 1/35 part

Similarly,

∵ In 39 days the work done by Stephen = 1

∴ In 1 day, the work done by Stephen = 1/39 part

Now, in 1 day, the work done by Kimberly and Stephen together

= In 1 day work done by Kimberly + In 1 day the work done by Stephen

= 1/35 + 1/39

= 39 + 35/1365

= 74/1365 part of work

This means in 1 day, 74/1365 part of work is done by Kimberly and Stephen working together.

Now, the number of days required to finish 74/1365 part of work by Kimberly + Stephen working together = 1

∴ the number of days required to finish 1 work by Kimberly + Stephen together

= 1/74/1365

= 1 × 1365/74 = 1365/74 days

= 18 33/74 days = or 18.446 days

Thus, Kimberly and Stephen working together will finish the work in 18 33/74 days = or 18.446 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Kimberly = 35 days

And the number of days required to finish the same work by Stephen = 39 days

Thus, the number of days required to finish the work Kimberly and Stephen working together = ?

Here a = 35 days

And, b = 39 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Kimberly and Stephen working together

= 35 × 39/35 + 39 days

= 1365/74 days

= 18 33/74 days or 18.446

Thus, Kimberly and Stephen together will finish the work in 18 33/74 days or 18.446 days Answer


Similar Questions

(1) If Michelle can finish the work in 41 days and Samuel can finish the same work in 45 days, then in how many days both can finish the work together?

(2) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?

(3) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 39 days, then in how many days both can finish the work together?

(4) If Eric can finish the work in 71 days and Gerald can finish the same work in 76 days, then in how many days both can finish the work together?

(5) Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?

(6) If Susan can finish the work in 15 days and Donald can finish the same work in 18 days, then in how many days both can finish the work together?

(7) If Steven can finish the work in 34 days and Jonathan can finish the same work in 38 days, then in how many days both can finish the work together?

(8) If Paul can finish the work in 36 days and Larry can finish the same work in 39 days, then in how many days both can finish the work together?

(9) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?

(10) Ryan can finish a work in 63 days. Gary can finish the same work in 68 days while Nicholas can finish the work in 73 days. How long will it take to finish it if they work together?