🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Brian can finish the work in 46 days and Raymond can finish the same work in 50 days, then in how many days both can finish the work together?


Correct Answer  23 23/24 days or 23.958 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Brian = 46 days

And, the number of days to finish the same work by Raymond = 50 days

Thus, the number of days to finish the work by Brian and Raymond together = ?

Here,

∵ In 46 days the work done by Brian = 1

∴ In 1 day, the work done by Brian = 1/46 part

Similarly,

∵ In 50 days the work done by Raymond = 1

∴ In 1 day, the work done by Raymond = 1/50 part

Now, in 1 day, the work done by Brian and Raymond together

= In 1 day work done by Brian + In 1 day the work done by Raymond

= 1/46 + 1/50

= 25 + 23/1150

= 48/1150 part of work

= 48 ÷ 2/1150 ÷ 2 part of work

= 24/575 part of work

This means, in 1 day, 24/575 part of the work is done by Brian and Raymond together.

Now, the number of days required to finish 24/575 part of work by Brian + Raymond working together = 1

∴ the number of days required to finish 1 work by Brian + Raymond together

= 1/24/575

= 1 × 575/24 = 575/24 days

= 23 23/24 days = or 23.958 days

Thus, Brian and Raymond working together will finish the work in 23 23/24 days = or 23.958 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Brian = 46 days

And the number of days required to finish the same work by Raymond = 50 days

Thus, the number of days required to finish the work Brian and Raymond working together = ?

Here a = 46 days

And, b = 50 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Brian and Raymond working together

= 46 × 50/46 + 50 days

= 2300/96 days

= 2300 ÷ 4/96 ÷ 4 = 575/24 days

= 23 23/24 days or 23.958

Thus, Brian and Raymond together will finish the work in 23 23/24 days or 23.958 days Answer


Similar Questions

(1) If Linda can finish the work in 12 days and Charles can finish the same work in 17 days, then in how many days both can finish the work together?

(2) Paul can finish a work in 39 days. Joshua can finish the same work in 44 days while Kenneth can finish the work in 49 days. How long will it take to finish it if they work together?

(3) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?

(4) If Sandra can finish the work in 31 days and Gary can finish the same work in 35 days, then in how many days both can finish the work together?

(5) Deborah can finish a work in 54 days. Rebecca can finish the same work in 59 days while Sharon can finish the work in 64 days. How long will it take to finish it if they work together?

(6) If Mary can finish the work in 25 days and Michael can finish the same work in 41 days, then in how many days both can finish the work together?

(7) Katherine can finish a work in 88 days. Debra can finish the same work in 93 days while Rachel can finish the work in 98 days. How long will it take to finish it if they work together?

(8) If Donna can finish the work in 39 days and Brandon can finish the same work in 43 days, then in how many days both can finish the work together?

(9) If Kevin can finish the work in 44 days and Frank can finish the same work in 48 days, then in how many days both can finish the work together?

(10) If Myra can finish the work in 25 days and Sophia can finish the same work in 15 days, then in how many days they both can finish the work working together?