🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Dorothy can finish the work in 47 days and Jack can finish the same work in 51 days, then in how many days both can finish the work together?


Correct Answer  24 45/98 days or 24.459 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Dorothy = 47 days

And, the number of days to finish the same work by Jack = 51 days

Thus, the number of days to finish the work by Dorothy and Jack together = ?

Here,

∵ In 47 days the work done by Dorothy = 1

∴ In 1 day, the work done by Dorothy = 1/47 part

Similarly,

∵ In 51 days the work done by Jack = 1

∴ In 1 day, the work done by Jack = 1/51 part

Now, in 1 day, the work done by Dorothy and Jack together

= In 1 day work done by Dorothy + In 1 day the work done by Jack

= 1/47 + 1/51

= 51 + 47/2397

= 98/2397 part of work

This means in 1 day, 98/2397 part of work is done by Dorothy and Jack working together.

Now, the number of days required to finish 98/2397 part of work by Dorothy + Jack working together = 1

∴ the number of days required to finish 1 work by Dorothy + Jack together

= 1/98/2397

= 1 × 2397/98 = 2397/98 days

= 24 45/98 days = or 24.459 days

Thus, Dorothy and Jack working together will finish the work in 24 45/98 days = or 24.459 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Dorothy = 47 days

And the number of days required to finish the same work by Jack = 51 days

Thus, the number of days required to finish the work Dorothy and Jack working together = ?

Here a = 47 days

And, b = 51 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Dorothy and Jack working together

= 47 × 51/47 + 51 days

= 2397/98 days

= 24 45/98 days or 24.459

Thus, Dorothy and Jack together will finish the work in 24 45/98 days or 24.459 days Answer


Similar Questions

(1) If Annie can finish a work in 2 days and Bobby can finish the same work in 3 days, then in how many days they both can finish the work working together?

(2) If Christine can finish the work in 90 days and Juan can finish the same work in 95 days, then in how many days both can finish the work together?

(3) If Robert can finish a work in 5 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?

(4) If Debra can finish the work in 92 days and Elijah can finish the same work in 97 days, then in how many days both can finish the work together?

(5) Donna can finish a work in 38 days. Michelle can finish the same work in 39 days while Carol can finish the work in 40 days. How long will it take to finish it if they work together?

(6) If Brenda can finish the work in 76 days and Arthur can finish the same work in 81 days, then in how many days both can finish the work together?

(7) If Daniel can finish the work in 27 days and Timothy can finish the same work in 32 days, then in how many days both can finish the work together?

(8) If Betty can finish the work in 27 days and Jason can finish the same work in 31 days, then in how many days both can finish the work together?

(9) If Charles can finish the work in 20 days and Kenneth can finish the same work in 23 days, then in how many days both can finish the work together?

(10) Timothy can finish a work in 49 days. Ronald can finish the same work in 50 days while Edward can finish the work in 51 days. How long will it take to finish it if they work together?