🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?


Correct Answer  24 24/25 days or 24.96 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by George = 48 days

And, the number of days to finish the same work by Dennis = 52 days

Thus, the number of days to finish the work by George and Dennis together = ?

Here,

∵ In 48 days the work done by George = 1

∴ In 1 day, the work done by George = 1/48 part

Similarly,

∵ In 52 days the work done by Dennis = 1

∴ In 1 day, the work done by Dennis = 1/52 part

Now, in 1 day, the work done by George and Dennis together

= In 1 day work done by George + In 1 day the work done by Dennis

= 1/48 + 1/52

= 13 + 12/624

= 25/624 part of work

This means in 1 day, 25/624 part of work is done by George and Dennis working together.

Now, the number of days required to finish 25/624 part of work by George + Dennis working together = 1

∴ the number of days required to finish 1 work by George + Dennis together

= 1/25/624

= 1 × 624/25 = 624/25 days

= 24 24/25 days = or 24.96 days

Thus, George and Dennis working together will finish the work in 24 24/25 days = or 24.96 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by George = 48 days

And the number of days required to finish the same work by Dennis = 52 days

Thus, the number of days required to finish the work George and Dennis working together = ?

Here a = 48 days

And, b = 52 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when George and Dennis working together

= 48 × 52/48 + 52 days

= 2496/100 days

= 2496 ÷ 4/100 ÷ 4 = 624/25 days

= 24 24/25 days or 24.96

Thus, George and Dennis together will finish the work in 24 24/25 days or 24.96 days Answer


Similar Questions

(1) If Jennifer can finish the work in 29 days and Joseph can finish the same work in 45 days, then in how many days both can finish the work together?

(2) If A can finish a work in 10 days and B can finish the same work in 15 days, then in how many days they both can finish the work working together?

(3) David can finish a work in 13 days. Richard can finish the same work in 18 days while Joseph can finish the work in 23 days. How long will it take to finish it if they work together?

(4) If Dorothy can finish the work in 47 days and Jack can finish the same work in 50 days, then in how many days both can finish the work together?

(5) If Matthew can finish the work in 26 days and Edward can finish the same work in 29 days, then in how many days both can finish the work together?

(6) If John can finish the work in 9 days and Richard can finish the same work in 14 days, then in how many days both can finish the work together?

(7) If Melissa can finish the work in 52 days and Jerry can finish the same work in 57 days, then in how many days both can finish the work together?

(8) Paul can finish a work in 35 days. Andrew can finish the same work in 36 days while Joshua can finish the work in 37 days. How long will it take to finish it if they work together?

(9) If Steven can finish the work in 34 days and Jonathan can finish the same work in 38 days, then in how many days both can finish the work together?

(10) If Brian can finish the work in 46 days and Raymond can finish the same work in 49 days, then in how many days both can finish the work together?