🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If James can finish the work in 2 days and John can finish the same work in 5 days, then in how many days both can finish the work together?


Correct Answer  1 3/7 days or 1.429 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by James = 2 days

And, the number of days to finish the same work by John = 5 days

Thus, the number of days to finish the work by James and John together = ?

Here,

∵ In 2 days the work done by James = 1

∴ In 1 day, the work done by James = 1/2 part

Similarly,

∵ In 5 days the work done by John = 1

∴ In 1 day, the work done by John = 1/5 part

Now, in 1 day, the work done by James and John together

= In 1 day work done by James + In 1 day the work done by John

= 1/2 + 1/5

= 5 + 2/10

= 7/10 part of work

This means in 1 day, 7/10 part of work is done by James and John working together.

Now, the number of days required to finish 7/10 part of work by James + John working together = 1

∴ the number of days required to finish 1 work by James + John together

= 1/7/10

= 1 × 10/7 = 10/7 days

= 1 3/7 days = or 1.429 days

Thus, James and John working together will finish the work in 1 3/7 days = or 1.429 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by James = 2 days

And the number of days required to finish the same work by John = 5 days

Thus, the number of days required to finish the work James and John working together = ?

Here a = 2 days

And, b = 5 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when James and John working together

= 2 × 5/2 + 5 days

= 10/7 days

= 1 3/7 days or 1.429

Thus, James and John together will finish the work in 1 3/7 days or 1.429 days Answer


Similar Questions

(1) If Sarah can finish the work in 22 days and Joshua can finish the same work in 27 days, then in how many days both can finish the work together?

(2) If Patricia can finish the work in 8 days and William can finish the same work in 13 days, then in how many days both can finish the work together?

(3) If Susan can finish the work in 15 days and Donald can finish the same work in 18 days, then in how many days both can finish the work together?

(4) If Richard can finish the work in 17 days and Mark can finish the same work in 22 days, then in how many days both can finish the work together?

(5) Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?

(6) If Dorothy can finish the work in 47 days and Jack can finish the same work in 51 days, then in how many days both can finish the work together?

(7) Dorothy can finish a work in 46 days. Melissa can finish the same work in 47 days while Deborah can finish the work in 48 days. How long will it take to finish it if they work together?

(8) If Annie can finish a work in 6 days and Bobby can finish the same work in 12 days, then in how many days they both can finish the work working together?

(9) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 39 days, then in how many days both can finish the work together?

(10) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?