🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Patricia can finish the work in 5 days and William can finish the same work in 8 days, then in how many days both can finish the work together?


Correct Answer  3 1/13 days or 3.077 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Patricia = 5 days

And, the number of days to finish the same work by William = 8 days

Thus, the number of days to finish the work by Patricia and William together = ?

Here,

∵ In 5 days the work done by Patricia = 1

∴ In 1 day, the work done by Patricia = 1/5 part

Similarly,

∵ In 8 days the work done by William = 1

∴ In 1 day, the work done by William = 1/8 part

Now, in 1 day, the work done by Patricia and William together

= In 1 day work done by Patricia + In 1 day the work done by William

= 1/5 + 1/8

= 8 + 5/40

= 13/40 part of work

This means in 1 day, 13/40 part of work is done by Patricia and William working together.

Now, the number of days required to finish 13/40 part of work by Patricia + William working together = 1

∴ the number of days required to finish 1 work by Patricia + William together

= 1/13/40

= 1 × 40/13 = 40/13 days

= 3 1/13 days = or 3.077 days

Thus, Patricia and William working together will finish the work in 3 1/13 days = or 3.077 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Patricia = 5 days

And the number of days required to finish the same work by William = 8 days

Thus, the number of days required to finish the work Patricia and William working together = ?

Here a = 5 days

And, b = 8 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Patricia and William working together

= 5 × 8/5 + 8 days

= 40/13 days

= 3 1/13 days or 3.077

Thus, Patricia and William together will finish the work in 3 1/13 days or 3.077 days Answer


Similar Questions

(1) Michael can finish a work in 11 days. William can finish the same work in 16 days while Richard can finish the work in 21 days. How long will it take to finish it if they work together?

(2) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?

(3) If Rachel can finish the work in 94 days and Roy can finish the same work in 99 days, then in how many days both can finish the work together?

(4) If Richard can finish the work in 36 days and Mark can finish the same work in 52 days, then in how many days both can finish the work together?

(5) Sandra can finish a work in 34 days. Kimberly can finish the same work in 39 days while Emily can finish the work in 44 days. How long will it take to finish it if they work together?

(6) If Helen can finish the work in 84 days and Bruce can finish the same work in 89 days, then in how many days both can finish the work together?

(7) If Nancy can finish the work in 28 days and Ronald can finish the same work in 33 days, then in how many days both can finish the work together?

(8) Susan can finish a work in 18 days. Sarah can finish the same work in 23 days while Karen can finish the work in 28 days. How long will it take to finish it if they work together?

(9) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(10) Debra can finish a work in 92 days. Carolyn can finish the same work in 97 days while Janet can finish the work in 102 days. How long will it take to finish it if they work together?