🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 14 days, then in how many days both can finish the work together?


Correct Answer  6 4/25 days or 6.16 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Elizabeth = 11 days

And, the number of days to finish the same work by Daniel = 14 days

Thus, the number of days to finish the work by Elizabeth and Daniel together = ?

Here,

∵ In 11 days the work done by Elizabeth = 1

∴ In 1 day, the work done by Elizabeth = 1/11 part

Similarly,

∵ In 14 days the work done by Daniel = 1

∴ In 1 day, the work done by Daniel = 1/14 part

Now, in 1 day, the work done by Elizabeth and Daniel together

= In 1 day work done by Elizabeth + In 1 day the work done by Daniel

= 1/11 + 1/14

= 14 + 11/154

= 25/154 part of work

This means in 1 day, 25/154 part of work is done by Elizabeth and Daniel working together.

Now, the number of days required to finish 25/154 part of work by Elizabeth + Daniel working together = 1

∴ the number of days required to finish 1 work by Elizabeth + Daniel together

= 1/25/154

= 1 × 154/25 = 154/25 days

= 6 4/25 days = or 6.16 days

Thus, Elizabeth and Daniel working together will finish the work in 6 4/25 days = or 6.16 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Elizabeth = 11 days

And the number of days required to finish the same work by Daniel = 14 days

Thus, the number of days required to finish the work Elizabeth and Daniel working together = ?

Here a = 11 days

And, b = 14 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Elizabeth and Daniel working together

= 11 × 14/11 + 14 days

= 154/25 days

= 6 4/25 days or 6.16

Thus, Elizabeth and Daniel together will finish the work in 6 4/25 days or 6.16 days Answer


Similar Questions

(1) If Ashley can finish the work in 33 days and Eric can finish the same work in 37 days, then in how many days both can finish the work together?

(2) Brian can finish a work in 49 days. Timothy can finish the same work in 54 days while Ronald can finish the work in 59 days. How long will it take to finish it if they work together?

(3) If Annie can finish a work in 6 days and Bobby can finish the same work in 12 days, then in how many days they both can finish the work working together?

(4) Lisa can finish a work in 26 days. Betty can finish the same work in 31 days while Margaret can finish the work in 36 days. How long will it take to finish it if they work together?

(5) Paul can finish a work in 39 days. Joshua can finish the same work in 44 days while Kenneth can finish the work in 49 days. How long will it take to finish it if they work together?

(6) Thomas can finish a work in 17 days. Charles can finish the same work in 18 days while Christopher can finish the work in 19 days. How long will it take to finish it if they work together?

(7) If Joseph can finish the work in 19 days and Steven can finish the same work in 24 days, then in how many days both can finish the work together?

(8) If Charles can finish the work in 20 days and Kenneth can finish the same work in 24 days, then in how many days both can finish the work together?

(9) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?

(10) Amanda can finish a work in 44 days. Dorothy can finish the same work in 45 days while Melissa can finish the work in 46 days. How long will it take to finish it if they work together?