🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?


Correct Answer  6 2/3 days or 6.667 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by William = 12 days

And, the number of days to finish the same work by Matthew = 15 days

Thus, the number of days to finish the work by William and Matthew together = ?

Here,

∵ In 12 days the work done by William = 1

∴ In 1 day, the work done by William = 1/12 part

Similarly,

∵ In 15 days the work done by Matthew = 1

∴ In 1 day, the work done by Matthew = 1/15 part

Now, in 1 day, the work done by William and Matthew together

= In 1 day work done by William + In 1 day the work done by Matthew

= 1/12 + 1/15

= 5 + 4/60

= 9/60 part of work

= 9 ÷ 3/60 ÷ 3 part of work

= 3/20 part of work

This means, in 1 day, 3/20 part of the work is done by William and Matthew together.

Now, the number of days required to finish 3/20 part of work by William + Matthew working together = 1

∴ the number of days required to finish 1 work by William + Matthew together

= 1/3/20

= 1 × 20/3 = 20/3 days

= 6 2/3 days = or 6.667 days

Thus, William and Matthew working together will finish the work in 6 2/3 days = or 6.667 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by William = 12 days

And the number of days required to finish the same work by Matthew = 15 days

Thus, the number of days required to finish the work William and Matthew working together = ?

Here a = 12 days

And, b = 15 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when William and Matthew working together

= 12 × 15/12 + 15 days

= 180/27 days

= 180 ÷ 9/27 ÷ 9 = 20/3 days

= 6 2/3 days or 6.667

Thus, William and Matthew together will finish the work in 6 2/3 days or 6.667 days Answer


Similar Questions

(1) Anna can finish a work in 74 days. Pamela can finish the same work in 79 days while Emma can finish the work in 84 days. How long will it take to finish it if they work together?

(2) Nicole can finish a work in 82 days. Samantha can finish the same work in 87 days while Katherine can finish the work in 92 days. How long will it take to finish it if they work together?

(3) If Lisa can finish the work in 23 days and George can finish the same work in 27 days, then in how many days both can finish the work together?

(4) Stephen can finish a work in 75 days. Justin can finish the same work in 80 days while Scott can finish the work in 85 days. How long will it take to finish it if they work together?

(5) Ryan can finish a work in 63 days. Gary can finish the same work in 68 days while Nicholas can finish the work in 73 days. How long will it take to finish it if they work together?

(6) Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?

(7) Karen can finish a work in 20 days. Lisa can finish the same work in 21 days while Nancy can finish the work in 22 days. How long will it take to finish it if they work together?

(8) If Richard can finish the work in 36 days and Mark can finish the same work in 52 days, then in how many days both can finish the work together?

(9) Brenda can finish a work in 76 days. Emma can finish the same work in 81 days while Nicole can finish the work in 86 days. How long will it take to finish it if they work together?