🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Steven can finish the work in 34 days and Jonathan can finish the same work in 37 days, then in how many days both can finish the work together?


Correct Answer  17 51/71 days or 17.718 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Steven = 34 days

And, the number of days to finish the same work by Jonathan = 37 days

Thus, the number of days to finish the work by Steven and Jonathan together = ?

Here,

∵ In 34 days the work done by Steven = 1

∴ In 1 day, the work done by Steven = 1/34 part

Similarly,

∵ In 37 days the work done by Jonathan = 1

∴ In 1 day, the work done by Jonathan = 1/37 part

Now, in 1 day, the work done by Steven and Jonathan together

= In 1 day work done by Steven + In 1 day the work done by Jonathan

= 1/34 + 1/37

= 37 + 34/1258

= 71/1258 part of work

This means in 1 day, 71/1258 part of work is done by Steven and Jonathan working together.

Now, the number of days required to finish 71/1258 part of work by Steven + Jonathan working together = 1

∴ the number of days required to finish 1 work by Steven + Jonathan together

= 1/71/1258

= 1 × 1258/71 = 1258/71 days

= 17 51/71 days = or 17.718 days

Thus, Steven and Jonathan working together will finish the work in 17 51/71 days = or 17.718 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Steven = 34 days

And the number of days required to finish the same work by Jonathan = 37 days

Thus, the number of days required to finish the work Steven and Jonathan working together = ?

Here a = 34 days

And, b = 37 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Steven and Jonathan working together

= 34 × 37/34 + 37 days

= 1258/71 days

= 17 51/71 days or 17.718

Thus, Steven and Jonathan together will finish the work in 17 51/71 days or 17.718 days Answer


Similar Questions

(1) Brandon can finish a work in 83 days. Samuel can finish the same work in 88 days while Gregory can finish the work in 93 days. How long will it take to finish it if they work together?

(2) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?

(3) Emily can finish a work in 40 days. Michelle can finish the same work in 45 days while Carol can finish the work in 50 days. How long will it take to finish it if they work together?

(4) John can finish a work in 9 days. David can finish the same work in 14 days while William can finish the work in 19 days. How long will it take to finish it if they work together?

(5) If Sarah can finish the work in 19 days and Joshua can finish the same work in 23 days, then in how many days both can finish the work together?

(6) If Jack can finish a work in 8 days and Bill can finish the same work in 12 days, then in how many days they both can finish the work working together?

(7) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?

(8) If Susan can finish the work in 15 days and Donald can finish the same work in 19 days, then in how many days both can finish the work together?

(9) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(10) Brenda can finish a work in 76 days. Emma can finish the same work in 81 days while Nicole can finish the work in 86 days. How long will it take to finish it if they work together?