🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Robert can finish the work in 7 days and David can finish the same work in 12 days, then in how many days both can finish the work together?


Correct Answer  4 8/19 days or 4.421 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Robert = 7 days

And, the number of days to finish the same work by David = 12 days

Thus, the number of days to finish the work by Robert and David together = ?

Here,

∵ In 7 days the work done by Robert = 1

∴ In 1 day, the work done by Robert = 1/7 part

Similarly,

∵ In 12 days the work done by David = 1

∴ In 1 day, the work done by David = 1/12 part

Now, in 1 day, the work done by Robert and David together

= In 1 day work done by Robert + In 1 day the work done by David

= 1/7 + 1/12

= 12 + 7/84

= 19/84 part of work

This means in 1 day, 19/84 part of work is done by Robert and David working together.

Now, the number of days required to finish 19/84 part of work by Robert + David working together = 1

∴ the number of days required to finish 1 work by Robert + David together

= 1/19/84

= 1 × 84/19 = 84/19 days

= 4 8/19 days = or 4.421 days

Thus, Robert and David working together will finish the work in 4 8/19 days = or 4.421 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Robert = 7 days

And the number of days required to finish the same work by David = 12 days

Thus, the number of days required to finish the work Robert and David working together = ?

Here a = 7 days

And, b = 12 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Robert and David working together

= 7 × 12/7 + 12 days

= 84/19 days

= 4 8/19 days or 4.421

Thus, Robert and David together will finish the work in 4 8/19 days or 4.421 days Answer


Similar Questions

(1) If Frank can finish the work in 93 days and Randy can finish the same work in 98 days, then in how many days both can finish the work together?

(2) Timothy can finish a work in 53 days. Edward can finish the same work in 58 days while Jason can finish the work in 63 days. How long will it take to finish it if they work together?

(3) Matthew can finish a work in 25 days. Anthony can finish the same work in 26 days while Mark can finish the work in 27 days. How long will it take to finish it if they work together?

(4) If Cynthia can finish the work in 64 days and Walter can finish the same work in 69 days, then in how many days both can finish the work together?

(5) If Sandra can finish the work in 34 days and Gary can finish the same work in 39 days, then in how many days both can finish the work together?

(6) If Paul can finish the work in 36 days and Larry can finish the same work in 39 days, then in how many days both can finish the work together?

(7) Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?

(8) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?

(9) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?

(10) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?