🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Patricia can finish the work in 8 days and William can finish the same work in 13 days, then in how many days both can finish the work together?


Correct Answer  4 20/21 days or 4.952 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Patricia = 8 days

And, the number of days to finish the same work by William = 13 days

Thus, the number of days to finish the work by Patricia and William together = ?

Here,

∵ In 8 days the work done by Patricia = 1

∴ In 1 day, the work done by Patricia = 1/8 part

Similarly,

∵ In 13 days the work done by William = 1

∴ In 1 day, the work done by William = 1/13 part

Now, in 1 day, the work done by Patricia and William together

= In 1 day work done by Patricia + In 1 day the work done by William

= 1/8 + 1/13

= 13 + 8/104

= 21/104 part of work

This means in 1 day, 21/104 part of work is done by Patricia and William working together.

Now, the number of days required to finish 21/104 part of work by Patricia + William working together = 1

∴ the number of days required to finish 1 work by Patricia + William together

= 1/21/104

= 1 × 104/21 = 104/21 days

= 4 20/21 days = or 4.952 days

Thus, Patricia and William working together will finish the work in 4 20/21 days = or 4.952 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Patricia = 8 days

And the number of days required to finish the same work by William = 13 days

Thus, the number of days required to finish the work Patricia and William working together = ?

Here a = 8 days

And, b = 13 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Patricia and William working together

= 8 × 13/8 + 13 days

= 104/21 days

= 4 20/21 days or 4.952

Thus, Patricia and William together will finish the work in 4 20/21 days or 4.952 days Answer


Similar Questions

(1) If Barbara can finish the work in 35 days and Anthony can finish the same work in 51 days, then in how many days both can finish the work together?

(2) Melissa can finish a work in 52 days. Stephanie can finish the same work in 57 days while Rebecca can finish the work in 62 days. How long will it take to finish it if they work together?

(3) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?

(4) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?

(5) If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?

(6) If Patricia can finish the work in 27 days and William can finish the same work in 43 days, then in how many days both can finish the work together?

(7) If Lisa can finish the work in 23 days and George can finish the same work in 26 days, then in how many days both can finish the work together?

(8) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(9) Steven can finish a work in 37 days. Andrew can finish the same work in 42 days while Joshua can finish the work in 47 days. How long will it take to finish it if they work together?

(10) If Amy can finish the work in 68 days and Keith can finish the same work in 73 days, then in how many days both can finish the work together?