🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If David can finish the work in 13 days and Christopher can finish the same work in 18 days, then in how many days both can finish the work together?


Correct Answer  7 17/31 days or 7.548 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by David = 13 days

And, the number of days to finish the same work by Christopher = 18 days

Thus, the number of days to finish the work by David and Christopher together = ?

Here,

∵ In 13 days the work done by David = 1

∴ In 1 day, the work done by David = 1/13 part

Similarly,

∵ In 18 days the work done by Christopher = 1

∴ In 1 day, the work done by Christopher = 1/18 part

Now, in 1 day, the work done by David and Christopher together

= In 1 day work done by David + In 1 day the work done by Christopher

= 1/13 + 1/18

= 18 + 13/234

= 31/234 part of work

This means in 1 day, 31/234 part of work is done by David and Christopher working together.

Now, the number of days required to finish 31/234 part of work by David + Christopher working together = 1

∴ the number of days required to finish 1 work by David + Christopher together

= 1/31/234

= 1 × 234/31 = 234/31 days

= 7 17/31 days = or 7.548 days

Thus, David and Christopher working together will finish the work in 7 17/31 days = or 7.548 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by David = 13 days

And the number of days required to finish the same work by Christopher = 18 days

Thus, the number of days required to finish the work David and Christopher working together = ?

Here a = 13 days

And, b = 18 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when David and Christopher working together

= 13 × 18/13 + 18 days

= 234/31 days

= 7 17/31 days or 7.548

Thus, David and Christopher together will finish the work in 7 17/31 days or 7.548 days Answer


Similar Questions

(1) Eric can finish a work in 71 days. Stephen can finish the same work in 76 days while Larry can finish the work in 81 days. How long will it take to finish it if they work together?

(2) If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?

(3) Mark can finish a work in 29 days. Donald can finish the same work in 30 days while Steven can finish the work in 31 days. How long will it take to finish it if they work together?

(4) Richard can finish a work in 13 days. Joseph can finish the same work in 14 days while Thomas can finish the work in 15 days. How long will it take to finish it if they work together?

(5) If Mark can finish the work in 30 days and Jacob can finish the same work in 33 days, then in how many days both can finish the work together?

(6) If Daniel can finish the work in 24 days and Timothy can finish the same work in 27 days, then in how many days both can finish the work together?

(7) If Lisa can finish the work in 23 days and George can finish the same work in 27 days, then in how many days both can finish the work together?

(8) Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?

(9) Charles can finish a work in 23 days. Daniel can finish the same work in 28 days while Matthew can finish the work in 33 days. How long will it take to finish it if they work together?

(10) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?