🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Barbara can finish the work in 16 days and Anthony can finish the same work in 21 days, then in how many days both can finish the work together?


Correct Answer  9 3/37 days or 9.081 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Barbara = 16 days

And, the number of days to finish the same work by Anthony = 21 days

Thus, the number of days to finish the work by Barbara and Anthony together = ?

Here,

∵ In 16 days the work done by Barbara = 1

∴ In 1 day, the work done by Barbara = 1/16 part

Similarly,

∵ In 21 days the work done by Anthony = 1

∴ In 1 day, the work done by Anthony = 1/21 part

Now, in 1 day, the work done by Barbara and Anthony together

= In 1 day work done by Barbara + In 1 day the work done by Anthony

= 1/16 + 1/21

= 21 + 16/336

= 37/336 part of work

This means in 1 day, 37/336 part of work is done by Barbara and Anthony working together.

Now, the number of days required to finish 37/336 part of work by Barbara + Anthony working together = 1

∴ the number of days required to finish 1 work by Barbara + Anthony together

= 1/37/336

= 1 × 336/37 = 336/37 days

= 9 3/37 days = or 9.081 days

Thus, Barbara and Anthony working together will finish the work in 9 3/37 days = or 9.081 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Barbara = 16 days

And the number of days required to finish the same work by Anthony = 21 days

Thus, the number of days required to finish the work Barbara and Anthony working together = ?

Here a = 16 days

And, b = 21 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Barbara and Anthony working together

= 16 × 21/16 + 21 days

= 336/37 days

= 9 3/37 days or 9.081

Thus, Barbara and Anthony together will finish the work in 9 3/37 days or 9.081 days Answer


Similar Questions

(1) If Donald can finish the work in 32 days and Nicholas can finish the same work in 35 days, then in how many days both can finish the work together?

(2) Melissa can finish a work in 48 days. Deborah can finish the same work in 49 days while Stephanie can finish the work in 50 days. How long will it take to finish it if they work together?

(3) Gary can finish a work in 67 days. Eric can finish the same work in 72 days while Jonathan can finish the work in 77 days. How long will it take to finish it if they work together?

(4) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(5) If Ashley can finish the work in 33 days and Eric can finish the same work in 37 days, then in how many days both can finish the work together?

(6) If Myra can finish the work in 25 days and Sophia can finish the same work in 15 days, then in how many days they both can finish the work working together?

(7) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(8) Robert can finish a work in 7 days. Michael can finish the same work in 12 days while David can finish the work in 17 days. How long will it take to finish it if they work together?

(9) Alexander can finish a work in 91 days. Patrick can finish the same work in 96 days while Raymond can finish the work in 101 days. How long will it take to finish it if they work together?

(10) Kenneth can finish a work in 45 days. Brian can finish the same work in 50 days while George can finish the work in 55 days. How long will it take to finish it if they work together?