Question : If Richard can finish the work in 17 days and Mark can finish the same work in 22 days, then in how many days both can finish the work together?
Correct Answer 9 23/39 days or 9.59 days
Solution & Explanation
Solution
Given,
The number of days to finish the work by Richard = 17 days
And, the number of days to finish the same work by Mark = 22 days
Thus, the number of days to finish the work by Richard and Mark together = ?
Here,
∵ In 17 days the work done by Richard = 1
∴ In 1 day, the work done by Richard = 1/17 part
Similarly,
∵ In 22 days the work done by Mark = 1
∴ In 1 day, the work done by Mark = 1/22 part
Now, in 1 day, the work done by Richard and Mark together
= In 1 day work done by Richard + In 1 day the work done by Mark
= 1/17 + 1/22
= 22 + 17/374
= 39/374 part of work
This means in 1 day, 39/374 part of work is done by Richard and Mark working together.
Now, the number of days required to finish 39/374 part of work by Richard + Mark working together = 1
∴ the number of days required to finish 1 work by Richard + Mark together
= 1/39/374
= 1 × 374/39 = 374/39 days
= 9 23/39 days = or 9.59 days
Thus, Richard and Mark working together will finish the work in 9 23/39 days = or 9.59 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.
Here given,
The number of days required to finish the work by Richard = 17 days
And the number of days required to finish the same work by Mark = 22 days
Thus, the number of days required to finish the work Richard and Mark working together = ?
Here a = 17 days
And, b = 22 days
Thus, using formula a × b/a + b days
The number of days required to finish the work when Richard and Mark working together
= 17 × 22/17 + 22 days
= 374/39 days
= 9 23/39 days or 9.59
Thus, Richard and Mark together will finish the work in 9 23/39 days or 9.59 days Answer
Similar Questions