🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?


Correct Answer  11 1/9 days or 11.111 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Jessica = 20 days

And, the number of days to finish the same work by Paul = 25 days

Thus, the number of days to finish the work by Jessica and Paul together = ?

Here,

∵ In 20 days the work done by Jessica = 1

∴ In 1 day, the work done by Jessica = 1/20 part

Similarly,

∵ In 25 days the work done by Paul = 1

∴ In 1 day, the work done by Paul = 1/25 part

Now, in 1 day, the work done by Jessica and Paul together

= In 1 day work done by Jessica + In 1 day the work done by Paul

= 1/20 + 1/25

= 5 + 4/100

= 9/100 part of work

This means in 1 day, 9/100 part of work is done by Jessica and Paul working together.

Now, the number of days required to finish 9/100 part of work by Jessica + Paul working together = 1

∴ the number of days required to finish 1 work by Jessica + Paul together

= 1/9/100

= 1 × 100/9 = 100/9 days

= 11 1/9 days = or 11.111 days

Thus, Jessica and Paul working together will finish the work in 11 1/9 days = or 11.111 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Jessica = 20 days

And the number of days required to finish the same work by Paul = 25 days

Thus, the number of days required to finish the work Jessica and Paul working together = ?

Here a = 20 days

And, b = 25 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Jessica and Paul working together

= 20 × 25/20 + 25 days

= 500/45 days

= 500 ÷ 5/45 ÷ 5 = 100/9 days

= 11 1/9 days or 11.111

Thus, Jessica and Paul together will finish the work in 11 1/9 days or 11.111 days Answer


Similar Questions

(1) Jack can finish a work in 99 days. Jerry can finish the same work in 104 days while Tyler can finish the work in 109 days. How long will it take to finish it if they work together?

(2) If Anna can finish the work in 74 days and Austin can finish the same work in 79 days, then in how many days both can finish the work together?

(3) Elizabeth can finish a work in 14 days. Susan can finish the same work in 19 days while Jessica can finish the work in 24 days. How long will it take to finish it if they work together?

(4) If Richard can finish the work in 36 days and Mark can finish the same work in 52 days, then in how many days both can finish the work together?

(5) Christine can finish a work in 90 days. Rachel can finish the same work in 95 days while Carolyn can finish the work in 100 days. How long will it take to finish it if they work together?

(6) If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 15 days, then in how many days both can finish the work together?

(7) If John can finish the work in 28 days and Richard can finish the same work in 44 days, then in how many days both can finish the work together?

(8) Matthew can finish a work in 25 days. Anthony can finish the same work in 26 days while Mark can finish the work in 27 days. How long will it take to finish it if they work together?

(9) Nancy can finish a work in 24 days. Betty can finish the same work in 25 days while Margaret can finish the work in 26 days. How long will it take to finish it if they work together?

(10) Betty can finish a work in 26 days. Margaret can finish the same work in 27 days while Sandra can finish the work in 28 days. How long will it take to finish it if they work together?