🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?


Correct Answer  11 1/9 days or 11.111 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Jessica = 20 days

And, the number of days to finish the same work by Paul = 25 days

Thus, the number of days to finish the work by Jessica and Paul together = ?

Here,

∵ In 20 days the work done by Jessica = 1

∴ In 1 day, the work done by Jessica = 1/20 part

Similarly,

∵ In 25 days the work done by Paul = 1

∴ In 1 day, the work done by Paul = 1/25 part

Now, in 1 day, the work done by Jessica and Paul together

= In 1 day work done by Jessica + In 1 day the work done by Paul

= 1/20 + 1/25

= 5 + 4/100

= 9/100 part of work

This means in 1 day, 9/100 part of work is done by Jessica and Paul working together.

Now, the number of days required to finish 9/100 part of work by Jessica + Paul working together = 1

∴ the number of days required to finish 1 work by Jessica + Paul together

= 1/9/100

= 1 × 100/9 = 100/9 days

= 11 1/9 days = or 11.111 days

Thus, Jessica and Paul working together will finish the work in 11 1/9 days = or 11.111 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Jessica = 20 days

And the number of days required to finish the same work by Paul = 25 days

Thus, the number of days required to finish the work Jessica and Paul working together = ?

Here a = 20 days

And, b = 25 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Jessica and Paul working together

= 20 × 25/20 + 25 days

= 500/45 days

= 500 ÷ 5/45 ÷ 5 = 100/9 days

= 11 1/9 days or 11.111

Thus, Jessica and Paul together will finish the work in 11 1/9 days or 11.111 days Answer


Similar Questions

(1) If Daniel can finish the work in 27 days and Timothy can finish the same work in 32 days, then in how many days both can finish the work together?

(2) If Myra can finish the work in 15 days and Sophia can finish the same work in 20 days, then in how many days they both can finish the work working together?

(3) Michelle can finish a work in 40 days. Carol can finish the same work in 41 days while Amanda can finish the work in 42 days. How long will it take to finish it if they work together?

(4) Emma can finish a work in 80 days. Helen can finish the same work in 85 days while Samantha can finish the work in 90 days. How long will it take to finish it if they work together?

(5) Carolyn can finish a work in 96 days. Catherine can finish the same work in 101 days while Maria can finish the work in 106 days. How long will it take to finish it if they work together?

(6) Barbara can finish a work in 12 days. Susan can finish the same work in 13 days while Jessica can finish the work in 14 days. How long will it take to finish it if they work together?

(7) If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?

(8) If Donna can finish the work in 39 days and Brandon can finish the same work in 42 days, then in how many days both can finish the work together?

(9) Samuel can finish a work in 87 days. Alexander can finish the same work in 92 days while Frank can finish the work in 97 days. How long will it take to finish it if they work together?

(10) If Daniel can finish the work in 24 days and Timothy can finish the same work in 27 days, then in how many days both can finish the work together?