🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?


Correct Answer  11 1/9 days or 11.111 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Jessica = 20 days

And, the number of days to finish the same work by Paul = 25 days

Thus, the number of days to finish the work by Jessica and Paul together = ?

Here,

∵ In 20 days the work done by Jessica = 1

∴ In 1 day, the work done by Jessica = 1/20 part

Similarly,

∵ In 25 days the work done by Paul = 1

∴ In 1 day, the work done by Paul = 1/25 part

Now, in 1 day, the work done by Jessica and Paul together

= In 1 day work done by Jessica + In 1 day the work done by Paul

= 1/20 + 1/25

= 5 + 4/100

= 9/100 part of work

This means in 1 day, 9/100 part of work is done by Jessica and Paul working together.

Now, the number of days required to finish 9/100 part of work by Jessica + Paul working together = 1

∴ the number of days required to finish 1 work by Jessica + Paul together

= 1/9/100

= 1 × 100/9 = 100/9 days

= 11 1/9 days = or 11.111 days

Thus, Jessica and Paul working together will finish the work in 11 1/9 days = or 11.111 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Jessica = 20 days

And the number of days required to finish the same work by Paul = 25 days

Thus, the number of days required to finish the work Jessica and Paul working together = ?

Here a = 20 days

And, b = 25 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Jessica and Paul working together

= 20 × 25/20 + 25 days

= 500/45 days

= 500 ÷ 5/45 ÷ 5 = 100/9 days

= 11 1/9 days or 11.111

Thus, Jessica and Paul together will finish the work in 11 1/9 days or 11.111 days Answer


Similar Questions

(1) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 44 days, then in how many days both can finish the work together?

(2) Donna can finish a work in 42 days. Carol can finish the same work in 47 days while Amanda can finish the work in 52 days. How long will it take to finish it if they work together?

(3) Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?

(4) Linda can finish a work in 8 days. Elizabeth can finish the same work in 9 days while Barbara can finish the work in 10 days. How long will it take to finish it if they work together?

(5) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(6) Jennifer can finish a work in 10 days. Elizabeth can finish the same work in 15 days while Barbara can finish the work in 20 days. How long will it take to finish it if they work together?

(7) If Joshua can finish the work in 43 days and Benjamin can finish the same work in 48 days, then in how many days both can finish the work together?

(8) Karen can finish a work in 24 days. Nancy can finish the same work in 29 days while Betty can finish the work in 34 days. How long will it take to finish it if they work together?

(9) Timothy can finish a work in 49 days. Ronald can finish the same work in 50 days while Edward can finish the work in 51 days. How long will it take to finish it if they work together?

(10) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?