🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Thomas can finish the work in 21 days and Andrew can finish the same work in 26 days, then in how many days both can finish the work together?


Correct Answer  11 29/47 days or 11.617 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Thomas = 21 days

And, the number of days to finish the same work by Andrew = 26 days

Thus, the number of days to finish the work by Thomas and Andrew together = ?

Here,

∵ In 21 days the work done by Thomas = 1

∴ In 1 day, the work done by Thomas = 1/21 part

Similarly,

∵ In 26 days the work done by Andrew = 1

∴ In 1 day, the work done by Andrew = 1/26 part

Now, in 1 day, the work done by Thomas and Andrew together

= In 1 day work done by Thomas + In 1 day the work done by Andrew

= 1/21 + 1/26

= 26 + 21/546

= 47/546 part of work

This means in 1 day, 47/546 part of work is done by Thomas and Andrew working together.

Now, the number of days required to finish 47/546 part of work by Thomas + Andrew working together = 1

∴ the number of days required to finish 1 work by Thomas + Andrew together

= 1/47/546

= 1 × 546/47 = 546/47 days

= 11 29/47 days = or 11.617 days

Thus, Thomas and Andrew working together will finish the work in 11 29/47 days = or 11.617 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Thomas = 21 days

And the number of days required to finish the same work by Andrew = 26 days

Thus, the number of days required to finish the work Thomas and Andrew working together = ?

Here a = 21 days

And, b = 26 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Thomas and Andrew working together

= 21 × 26/21 + 26 days

= 546/47 days

= 11 29/47 days or 11.617

Thus, Thomas and Andrew together will finish the work in 11 29/47 days or 11.617 days Answer


Similar Questions

(1) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(2) Linda can finish a work in 12 days. Barbara can finish the same work in 17 days while Susan can finish the work in 22 days. How long will it take to finish it if they work together?

(3) If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 14 days, then in how many days both can finish the work together?

(4) Margaret can finish a work in 32 days. Ashley can finish the same work in 37 days while Kimberly can finish the work in 42 days. How long will it take to finish it if they work together?

(5) Anthony can finish a work in 31 days. Donald can finish the same work in 36 days while Steven can finish the work in 41 days. How long will it take to finish it if they work together?

(6) Mark can finish a work in 33 days. Steven can finish the same work in 38 days while Paul can finish the work in 43 days. How long will it take to finish it if they work together?

(7) If Annie can finish a work in 3 days and Bobby can finish the same work in 6 days, then in how many days they both can finish the work working together?

(8) Betty can finish a work in 30 days. Sandra can finish the same work in 35 days while Ashley can finish the work in 40 days. How long will it take to finish it if they work together?

(9) If Pamela can finish the work in 78 days and Dylan can finish the same work in 83 days, then in how many days both can finish the work together?

(10) Nancy can finish a work in 24 days. Betty can finish the same work in 25 days while Margaret can finish the work in 26 days. How long will it take to finish it if they work together?