🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Karen can finish the work in 24 days and Kevin can finish the same work in 29 days, then in how many days both can finish the work together?


Correct Answer  13 7/53 days or 13.132 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Karen = 24 days

And, the number of days to finish the same work by Kevin = 29 days

Thus, the number of days to finish the work by Karen and Kevin together = ?

Here,

∵ In 24 days the work done by Karen = 1

∴ In 1 day, the work done by Karen = 1/24 part

Similarly,

∵ In 29 days the work done by Kevin = 1

∴ In 1 day, the work done by Kevin = 1/29 part

Now, in 1 day, the work done by Karen and Kevin together

= In 1 day work done by Karen + In 1 day the work done by Kevin

= 1/24 + 1/29

= 29 + 24/696

= 53/696 part of work

This means in 1 day, 53/696 part of work is done by Karen and Kevin working together.

Now, the number of days required to finish 53/696 part of work by Karen + Kevin working together = 1

∴ the number of days required to finish 1 work by Karen + Kevin together

= 1/53/696

= 1 × 696/53 = 696/53 days

= 13 7/53 days = or 13.132 days

Thus, Karen and Kevin working together will finish the work in 13 7/53 days = or 13.132 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Karen = 24 days

And the number of days required to finish the same work by Kevin = 29 days

Thus, the number of days required to finish the work Karen and Kevin working together = ?

Here a = 24 days

And, b = 29 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Karen and Kevin working together

= 24 × 29/24 + 29 days

= 696/53 days

= 13 7/53 days or 13.132

Thus, Karen and Kevin together will finish the work in 13 7/53 days or 13.132 days Answer


Similar Questions

(1) Mark can finish a work in 29 days. Donald can finish the same work in 30 days while Steven can finish the work in 31 days. How long will it take to finish it if they work together?

(2) If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?

(3) Robert can finish a work in 7 days. Michael can finish the same work in 12 days while David can finish the work in 17 days. How long will it take to finish it if they work together?

(4) If Matthew can finish the work in 26 days and Edward can finish the same work in 30 days, then in how many days both can finish the work together?

(5) If Brian can finish the work in 49 days and Raymond can finish the same work in 54 days, then in how many days both can finish the work together?

(6) If Barbara can finish the work in 16 days and Anthony can finish the same work in 21 days, then in how many days both can finish the work together?

(7) If John can finish the work in 6 days and Richard can finish the same work in 9 days, then in how many days both can finish the work together?

(8) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?

(9) If Donna can finish the work in 42 days and Brandon can finish the same work in 47 days, then in how many days both can finish the work together?

(10) If Christine can finish the work in 90 days and Juan can finish the same work in 95 days, then in how many days both can finish the work together?