🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Lisa can finish the work in 26 days and George can finish the same work in 31 days, then in how many days both can finish the work together?


Correct Answer  14 8/57 days or 14.14 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Lisa = 26 days

And, the number of days to finish the same work by George = 31 days

Thus, the number of days to finish the work by Lisa and George together = ?

Here,

∵ In 26 days the work done by Lisa = 1

∴ In 1 day, the work done by Lisa = 1/26 part

Similarly,

∵ In 31 days the work done by George = 1

∴ In 1 day, the work done by George = 1/31 part

Now, in 1 day, the work done by Lisa and George together

= In 1 day work done by Lisa + In 1 day the work done by George

= 1/26 + 1/31

= 31 + 26/806

= 57/806 part of work

This means in 1 day, 57/806 part of work is done by Lisa and George working together.

Now, the number of days required to finish 57/806 part of work by Lisa + George working together = 1

∴ the number of days required to finish 1 work by Lisa + George together

= 1/57/806

= 1 × 806/57 = 806/57 days

= 14 8/57 days = or 14.14 days

Thus, Lisa and George working together will finish the work in 14 8/57 days = or 14.14 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Lisa = 26 days

And the number of days required to finish the same work by George = 31 days

Thus, the number of days required to finish the work Lisa and George working together = ?

Here a = 26 days

And, b = 31 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Lisa and George working together

= 26 × 31/26 + 31 days

= 806/57 days

= 14 8/57 days or 14.14

Thus, Lisa and George together will finish the work in 14 8/57 days or 14.14 days Answer


Similar Questions

(1) If Justin can finish the work in 79 days and Jesse can finish the same work in 84 days, then in how many days both can finish the work together?

(2) If Joseph can finish the work in 16 days and Steven can finish the same work in 19 days, then in how many days both can finish the work together?

(3) If Jessica can finish the work in 17 days and Paul can finish the same work in 21 days, then in how many days both can finish the work together?

(4) If Margaret can finish the work in 29 days and Ryan can finish the same work in 32 days, then in how many days both can finish the work together?

(5) Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?

(6) If Catherine can finish the work in 100 days and Mason can finish the same work in 105 days, then in how many days both can finish the work together?

(7) If Donald can finish the work in 32 days and Nicholas can finish the same work in 36 days, then in how many days both can finish the work together?

(8) If Michael can finish the work in 30 days and Thomas can finish the same work in 46 days, then in how many days both can finish the work together?

(9) If Donald can finish the work in 35 days and Nicholas can finish the same work in 40 days, then in how many days both can finish the work together?

(10) Margaret can finish a work in 32 days. Ashley can finish the same work in 37 days while Kimberly can finish the work in 42 days. How long will it take to finish it if they work together?