Question : If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?
Correct Answer 16 44/67 days or 16.657 days
Solution & Explanation
Solution
Given,
The number of days to finish the work by Anthony = 31 days
And, the number of days to finish the same work by Jeffrey = 36 days
Thus, the number of days to finish the work by Anthony and Jeffrey together = ?
Here,
∵ In 31 days the work done by Anthony = 1
∴ In 1 day, the work done by Anthony = 1/31 part
Similarly,
∵ In 36 days the work done by Jeffrey = 1
∴ In 1 day, the work done by Jeffrey = 1/36 part
Now, in 1 day, the work done by Anthony and Jeffrey together
= In 1 day work done by Anthony + In 1 day the work done by Jeffrey
= 1/31 + 1/36
= 36 + 31/1116
= 67/1116 part of work
This means in 1 day, 67/1116 part of work is done by Anthony and Jeffrey working together.
Now, the number of days required to finish 67/1116 part of work by Anthony + Jeffrey working together = 1
∴ the number of days required to finish 1 work by Anthony + Jeffrey together
= 1/67/1116
= 1 × 1116/67 = 1116/67 days
= 16 44/67 days = or 16.657 days
Thus, Anthony and Jeffrey working together will finish the work in 16 44/67 days = or 16.657 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.
Here given,
The number of days required to finish the work by Anthony = 31 days
And the number of days required to finish the same work by Jeffrey = 36 days
Thus, the number of days required to finish the work Anthony and Jeffrey working together = ?
Here a = 31 days
And, b = 36 days
Thus, using formula a × b/a + b days
The number of days required to finish the work when Anthony and Jeffrey working together
= 31 × 36/31 + 36 days
= 1116/67 days
= 16 44/67 days or 16.657
Thus, Anthony and Jeffrey together will finish the work in 16 44/67 days or 16.657 days Answer
Similar Questions