🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Annie can finish a work in 6 days and Bobby can finish the same work in 12 days, then in how many days they both can finish the work working together?


Correct Answer  4 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Annie = 6 days

And, the number of days to finish the same work by Bobby = 12 days

Thus, the number of days to finish the work by Annie and Bobby working together = ?

Here, ∵ In 6 days the work done by Annie = 1

∴ In 1 day, the work done by Annie = 1/6 part

Similarly, ∵ In 12 days the work done by Bobby = 1

∴ In 1 day, the work done by Bobby = 1/12 part

Now, in 1 day, the work done by Annie and Bobby working together

= In 1 day work done by Annie + In 1 day the work done by Bobby

= 1/6 + 1/12

= 2 + 1/12

= 3 1/12 4 = 1/4 part of work

This means in 1 day, 1/4 part of work is done by Annie and Bobby working together.

Now, the number of days required to finish 1/4 part work by Annie + Bobby working together = 1

∴ the number of days required to finish 1 work by Robert + Bob working together

= 1/1/4

= 1 × 4/1 days = 4 days

Thus, Annie and Bobby working together will finish the work in 4 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in "a" days, and B can finish the same work in "b" days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days to finish the work by Annie =6 days

And, the number of days to finish the same work by Bobby = 12 days

Thus, the number of days to finish the work by Annie and Bobby working together = ?

Here "a" = 6 days

And, "b" = 12 days

Thus, using formula a × b/a + b days

The number of days require to finish the work when Annie and Bobby working together

= 6 × 12/6 + 12

= 72 4/18 = 4 days

Thus, Annie and Bobby working together will finish the work in 4 days Answer


Similar Questions

(1) If Carolyn can finish the work in 96 days and Ralph can finish the same work in 101 days, then in how many days both can finish the work together?

(2) Carol can finish a work in 46 days. Dorothy can finish the same work in 51 days while Melissa can finish the work in 56 days. How long will it take to finish it if they work together?

(3) Samantha can finish a work in 86 days. Christine can finish the same work in 91 days while Debra can finish the work in 96 days. How long will it take to finish it if they work together?

(4) If Shirley can finish the work in 72 days and Harold can finish the same work in 77 days, then in how many days both can finish the work together?

(5) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?

(6) Brian can finish a work in 49 days. Timothy can finish the same work in 54 days while Ronald can finish the work in 59 days. How long will it take to finish it if they work together?

(7) William can finish a work in 11 days. Richard can finish the same work in 12 days while Joseph can finish the work in 13 days. How long will it take to finish it if they work together?

(8) Joseph can finish a work in 19 days. Charles can finish the same work in 24 days while Christopher can finish the work in 29 days. How long will it take to finish it if they work together?

(9) Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?

(10) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?