Question : If Michelle can finish the work in 44 days and Samuel can finish the same work in 49 days, then in how many days both can finish the work together?
Correct Answer 23 17/93 days or 23.183 days
Solution & Explanation
Solution
Given,
The number of days to finish the work by Michelle = 44 days
And, the number of days to finish the same work by Samuel = 49 days
Thus, the number of days to finish the work by Michelle and Samuel together = ?
Here,
∵ In 44 days the work done by Michelle = 1
∴ In 1 day, the work done by Michelle = 1/44 part
Similarly,
∵ In 49 days the work done by Samuel = 1
∴ In 1 day, the work done by Samuel = 1/49 part
Now, in 1 day, the work done by Michelle and Samuel together
= In 1 day work done by Michelle + In 1 day the work done by Samuel
= 1/44 + 1/49
= 49 + 44/2156
= 93/2156 part of work
This means in 1 day, 93/2156 part of work is done by Michelle and Samuel working together.
Now, the number of days required to finish 93/2156 part of work by Michelle + Samuel working together = 1
∴ the number of days required to finish 1 work by Michelle + Samuel together
= 1/93/2156
= 1 × 2156/93 = 2156/93 days
= 23 17/93 days = or 23.183 days
Thus, Michelle and Samuel working together will finish the work in 23 17/93 days = or 23.183 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.
Here given,
The number of days required to finish the work by Michelle = 44 days
And the number of days required to finish the same work by Samuel = 49 days
Thus, the number of days required to finish the work Michelle and Samuel working together = ?
Here a = 44 days
And, b = 49 days
Thus, using formula a × b/a + b days
The number of days required to finish the work when Michelle and Samuel working together
= 44 × 49/44 + 49 days
= 2156/93 days
= 23 17/93 days or 23.183
Thus, Michelle and Samuel together will finish the work in 23 17/93 days or 23.183 days Answer