🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Larry can finish the work in 77 days and Lawrence can finish the same work in 82 days, then in how many days both can finish the work together?


Correct Answer  39 113/159 days or 39.711 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Larry = 77 days

And, the number of days to finish the same work by Lawrence = 82 days

Thus, the number of days to finish the work by Larry and Lawrence together = ?

Here,

∵ In 77 days the work done by Larry = 1

∴ In 1 day, the work done by Larry = 1/77 part

Similarly,

∵ In 82 days the work done by Lawrence = 1

∴ In 1 day, the work done by Lawrence = 1/82 part

Now, in 1 day, the work done by Larry and Lawrence together

= In 1 day work done by Larry + In 1 day the work done by Lawrence

= 1/77 + 1/82

= 82 + 77/6314

= 159/6314 part of work

This means in 1 day, 159/6314 part of work is done by Larry and Lawrence working together.

Now, the number of days required to finish 159/6314 part of work by Larry + Lawrence working together = 1

∴ the number of days required to finish 1 work by Larry + Lawrence together

= 1/159/6314

= 1 × 6314/159 = 6314/159 days

= 39 113/159 days = or 39.711 days

Thus, Larry and Lawrence working together will finish the work in 39 113/159 days = or 39.711 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Larry = 77 days

And the number of days required to finish the same work by Lawrence = 82 days

Thus, the number of days required to finish the work Larry and Lawrence working together = ?

Here a = 77 days

And, b = 82 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Larry and Lawrence working together

= 77 × 82/77 + 82 days

= 6314/159 days

= 39 113/159 days or 39.711

Thus, Larry and Lawrence together will finish the work in 39 113/159 days or 39.711 days Answer


Similar Questions

(1) If Justin can finish the work in 79 days and Jesse can finish the same work in 84 days, then in how many days both can finish the work together?

(2) If Brian can finish the work in 49 days and Raymond can finish the same work in 54 days, then in how many days both can finish the work together?

(3) If Patricia can finish the work in 5 days and William can finish the same work in 9 days, then in how many days both can finish the work together?

(4) Jack can finish a work in 99 days. Jerry can finish the same work in 104 days while Tyler can finish the work in 109 days. How long will it take to finish it if they work together?

(5) If Jack can finish the work in 20 days and Bill can finish the same work in 30 days, then in how many days they both can finish the work working together?

(6) Donald can finish a work in 31 days. Steven can finish the same work in 32 days while Paul can finish the work in 33 days. How long will it take to finish it if they work together?

(7) Justin can finish a work in 79 days. Brandon can finish the same work in 84 days while Benjamin can finish the work in 89 days. How long will it take to finish it if they work together?

(8) If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?

(9) If Donna can finish the work in 42 days and Brandon can finish the same work in 47 days, then in how many days both can finish the work together?

(10) Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?