🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?


Correct Answer  49 143/199 days or 49.719 days

Solution & Explanation

Solution

Given,

The number of days to finish the work by Raymond = 97 days

And, the number of days to finish the same work by Eugene = 102 days

Thus, the number of days to finish the work by Raymond and Eugene together = ?

Here,

∵ In 97 days the work done by Raymond = 1

∴ In 1 day, the work done by Raymond = 1/97 part

Similarly,

∵ In 102 days the work done by Eugene = 1

∴ In 1 day, the work done by Eugene = 1/102 part

Now, in 1 day, the work done by Raymond and Eugene together

= In 1 day work done by Raymond + In 1 day the work done by Eugene

= 1/97 + 1/102

= 102 + 97/9894

= 199/9894 part of work

This means in 1 day, 199/9894 part of work is done by Raymond and Eugene working together.

Now, the number of days required to finish 199/9894 part of work by Raymond + Eugene working together = 1

∴ the number of days required to finish 1 work by Raymond + Eugene together

= 1/199/9894

= 1 × 9894/199 = 9894/199 days

= 49 143/199 days = or 49.719 days

Thus, Raymond and Eugene working together will finish the work in 49 143/199 days = or 49.719 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Raymond = 97 days

And the number of days required to finish the same work by Eugene = 102 days

Thus, the number of days required to finish the work Raymond and Eugene working together = ?

Here a = 97 days

And, b = 102 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Raymond and Eugene working together

= 97 × 102/97 + 102 days

= 9894/199 days

= 49 143/199 days or 49.719

Thus, Raymond and Eugene together will finish the work in 49 143/199 days or 49.719 days Answer


Similar Questions

(1) Robert can finish a work in 7 days. Michael can finish the same work in 12 days while David can finish the work in 17 days. How long will it take to finish it if they work together?

(2) If Katherine can finish the work in 88 days and Willie can finish the same work in 93 days, then in how many days both can finish the work together?

(3) Margaret can finish a work in 28 days. Sandra can finish the same work in 29 days while Ashley can finish the work in 30 days. How long will it take to finish it if they work together?

(4) Betty can finish a work in 26 days. Margaret can finish the same work in 27 days while Sandra can finish the work in 28 days. How long will it take to finish it if they work together?

(5) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(6) Laura can finish a work in 62 days. Kathleen can finish the same work in 67 days while Amy can finish the work in 72 days. How long will it take to finish it if they work together?

(7) Jessica can finish a work in 16 days. Sarah can finish the same work in 17 days while Karen can finish the work in 18 days. How long will it take to finish it if they work together?

(8) If Dorothy can finish the work in 47 days and Jack can finish the same work in 50 days, then in how many days both can finish the work together?

(9) If Dorothy can finish the work in 50 days and Jack can finish the same work in 55 days, then in how many days both can finish the work together?

(10) If Catherine can finish the work in 100 days and Mason can finish the same work in 105 days, then in how many days both can finish the work together?