🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Christopher can finish a work in 25 days. Matthew can finish the same work in 30 days while Anthony can finish the work in 35 days. How long will it take to finish it if they work together?


Correct Answer  9 87/107 days or 9.813 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Christopher = 25 days

And, the number of days required to finish the same work by Matthew = 30 days

And, the number of days required to finish the same work by Anthony = 35 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 25 days the work is done by Christopher = 1

∴ The work done by Christopher in 1 day = 1/25

Similarly,

∵ In 30 days the work is done by Matthew = 1

∴ The work done by Matthew in 1 day = 1/30

Similarly,

∵ In 35 days the work is done by Anthony = 1

∴ The work done by Anthony in 1 day = 1/35 part

Now, the work done by Christopher, Matthew, and Anthony together in 1 day

= Christopher's 1 day work + Matthew's 1 day work + Anthony's 1 day work

= 1/25 + 1/30 + 1/35

= 42 + 35 + 30/1050

= 107/1050 part of work

This means in 1 day, 107/1050 part of work is done by Christopher, Matthew and Anthony working together.

Now, the number of days required to finish 107/1050 part of work by Christopher, Matthew, and Anthony working together = 1

∴ the number of days required to finish the whole work (1 work) by Christopher + Matthew + Anthony together

= 1/107/1050

= 1 × 1050/107 = 1050/107 days

= 9 87/107 days = or 9.813 days

Thus, Christopher, Matthew, and Anthony working together will finish the total work (1 work) in 9 87/107 days = or 9.813 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Christopher = 25 days

And the number of days required to finish the same work by Matthew = 30 days

And the number of days required to finish the work by Anthony = 35 days

Thus, the number of days required to finish the work by Christopher, Matthew, and Anthony together = ?

Here a = 25 days

And, b = 30 days

And, c = 35 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Christopher, Matthew, and Anthony working together

= 25 × 30 × 35/25 × 30 + 25 × 35 + 30 × 35 days

= 26250/750 + 875 + 1050 days

= 26250/2675 days

= 26250/2675 days

= 26250 ÷ 25/2675 ÷ 25 = 1050/107 days

= 9 87/107 days or 9.813

Thus, Christopher, Matthew, and Anthony together will finish the work in 9 87/107 days or 9.813 days Answer


Similar Questions

(1) If Jeffrey can finish the work in 61 days and Peter can finish the same work in 66 days, then in how many days both can finish the work together?

(2) Kenneth can finish a work in 41 days. Kevin can finish the same work in 42 days while Brian can finish the work in 43 days. How long will it take to finish it if they work together?

(3) Patrick can finish a work in 95 days. Jack can finish the same work in 100 days while Dennis can finish the work in 105 days. How long will it take to finish it if they work together?

(4) If Margaret can finish the work in 29 days and Ryan can finish the same work in 32 days, then in how many days both can finish the work together?

(5) Gary can finish a work in 67 days. Eric can finish the same work in 72 days while Jonathan can finish the work in 77 days. How long will it take to finish it if they work together?

(6) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?

(7) If Matthew can finish the work in 29 days and Edward can finish the same work in 34 days, then in how many days both can finish the work together?

(8) If Christopher can finish the work in 22 days and Brian can finish the same work in 25 days, then in how many days both can finish the work together?

(9) If Joshua can finish the work in 43 days and Benjamin can finish the same work in 48 days, then in how many days both can finish the work together?

(10) Matthew can finish a work in 25 days. Anthony can finish the same work in 26 days while Mark can finish the work in 27 days. How long will it take to finish it if they work together?