🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Lisa can finish a work in 26 days. Betty can finish the same work in 31 days while Margaret can finish the work in 36 days. How long will it take to finish it if they work together?


Correct Answer  10 218/1429 days or 10.153 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Lisa = 26 days

And, the number of days required to finish the same work by Betty = 31 days

And, the number of days required to finish the same work by Margaret = 36 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 26 days the work is done by Lisa = 1

∴ The work done by Lisa in 1 day = 1/26

Similarly,

∵ In 31 days the work is done by Betty = 1

∴ The work done by Betty in 1 day = 1/31

Similarly,

∵ In 36 days the work is done by Margaret = 1

∴ The work done by Margaret in 1 day = 1/36 part

Now, the work done by Lisa, Betty, and Margaret together in 1 day

= Lisa's 1 day work + Betty's 1 day work + Margaret's 1 day work

= 1/26 + 1/31 + 1/36

= 558 + 468 + 403/14508

= 1429/14508 part of work

This means in 1 day, 1429/14508 part of work is done by Lisa, Betty and Margaret working together.

Now, the number of days required to finish 1429/14508 part of work by Lisa, Betty, and Margaret working together = 1

∴ the number of days required to finish the whole work (1 work) by Lisa + Betty + Margaret together

= 1/1429/14508

= 1 × 14508/1429 = 14508/1429 days

= 10 218/1429 days = or 10.153 days

Thus, Lisa, Betty, and Margaret working together will finish the total work (1 work) in 10 218/1429 days = or 10.153 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Lisa = 26 days

And the number of days required to finish the same work by Betty = 31 days

And the number of days required to finish the work by Margaret = 36 days

Thus, the number of days required to finish the work by Lisa, Betty, and Margaret together = ?

Here a = 26 days

And, b = 31 days

And, c = 36 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Lisa, Betty, and Margaret working together

= 26 × 31 × 36/26 × 31 + 26 × 36 + 31 × 36 days

= 29016/806 + 936 + 1116 days

= 29016/2858 days

= 29016/2858 days

= 29016 ÷ 2/2858 ÷ 2 = 14508/1429 days

= 10 218/1429 days or 10.153

Thus, Lisa, Betty, and Margaret together will finish the work in 10 218/1429 days or 10.153 days Answer


Similar Questions

(1) Raymond can finish a work in 97 days. Dennis can finish the same work in 102 days while Jerry can finish the work in 107 days. How long will it take to finish it if they work together?

(2) If Susan can finish the work in 15 days and Donald can finish the same work in 19 days, then in how many days both can finish the work together?

(3) Michael can finish a work in 7 days. David can finish the same work in 8 days while William can finish the work in 9 days. How long will it take to finish it if they work together?

(4) Cynthia can finish a work in 64 days. Amy can finish the same work in 69 days while Angela can finish the work in 74 days. How long will it take to finish it if they work together?

(5) Donald can finish a work in 35 days. Paul can finish the same work in 40 days while Andrew can finish the work in 45 days. How long will it take to finish it if they work together?

(6) Justin can finish a work in 79 days. Brandon can finish the same work in 84 days while Benjamin can finish the work in 89 days. How long will it take to finish it if they work together?

(7) Matthew can finish a work in 25 days. Anthony can finish the same work in 26 days while Mark can finish the work in 27 days. How long will it take to finish it if they work together?

(8) If Sarah can finish the work in 19 days and Joshua can finish the same work in 22 days, then in how many days both can finish the work together?

(9) Donna can finish a work in 38 days. Michelle can finish the same work in 39 days while Carol can finish the work in 40 days. How long will it take to finish it if they work together?

(10) If Lisa can finish the work in 23 days and George can finish the same work in 27 days, then in how many days both can finish the work together?