🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Paul can finish a work in 39 days. Joshua can finish the same work in 44 days while Kenneth can finish the work in 49 days. How long will it take to finish it if they work together?


Correct Answer  14 3122/5783 days or 14.54 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Paul = 39 days

And, the number of days required to finish the same work by Joshua = 44 days

And, the number of days required to finish the same work by Kenneth = 49 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 39 days the work is done by Paul = 1

∴ The work done by Paul in 1 day = 1/39

Similarly,

∵ In 44 days the work is done by Joshua = 1

∴ The work done by Joshua in 1 day = 1/44

Similarly,

∵ In 49 days the work is done by Kenneth = 1

∴ The work done by Kenneth in 1 day = 1/49 part

Now, the work done by Paul, Joshua, and Kenneth together in 1 day

= Paul's 1 day work + Joshua's 1 day work + Kenneth's 1 day work

= 1/39 + 1/44 + 1/49

= 2156 + 1911 + 1716/84084

= 5783/84084 part of work

This means in 1 day, 5783/84084 part of work is done by Paul, Joshua and Kenneth working together.

Now, the number of days required to finish 5783/84084 part of work by Paul, Joshua, and Kenneth working together = 1

∴ the number of days required to finish the whole work (1 work) by Paul + Joshua + Kenneth together

= 1/5783/84084

= 1 × 84084/5783 = 84084/5783 days

= 14 3122/5783 days = or 14.54 days

Thus, Paul, Joshua, and Kenneth working together will finish the total work (1 work) in 14 3122/5783 days = or 14.54 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Paul = 39 days

And the number of days required to finish the same work by Joshua = 44 days

And the number of days required to finish the work by Kenneth = 49 days

Thus, the number of days required to finish the work by Paul, Joshua, and Kenneth together = ?

Here a = 39 days

And, b = 44 days

And, c = 49 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Paul, Joshua, and Kenneth working together

= 39 × 44 × 49/39 × 44 + 39 × 49 + 44 × 49 days

= 84084/1716 + 1911 + 2156 days

= 84084/5783 days

= 84084/5783 days

= 14 3122/5783 days or 14.54

Thus, Paul, Joshua, and Kenneth together will finish the work in 14 3122/5783 days or 14.54 days Answer


Similar Questions

(1) If Myra can finish the work in 15 days and Sophia can finish the same work in 20 days, then in how many days they both can finish the work working together?

(2) If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?

(3) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 38 days, then in how many days both can finish the work together?

(4) If Kathleen can finish the work in 66 days and Jeremy can finish the same work in 71 days, then in how many days both can finish the work together?

(5) Jennifer can finish a work in 10 days. Elizabeth can finish the same work in 15 days while Barbara can finish the work in 20 days. How long will it take to finish it if they work together?

(6) If Larry can finish the work in 77 days and Lawrence can finish the same work in 82 days, then in how many days both can finish the work together?

(7) If Robert can finish a work in 5 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?

(8) If Mark can finish the work in 30 days and Jacob can finish the same work in 33 days, then in how many days both can finish the work together?

(9) Edward can finish a work in 57 days. Jeffrey can finish the same work in 62 days while Ryan can finish the work in 67 days. How long will it take to finish it if they work together?

(10) If Brian can finish the work in 46 days and Raymond can finish the same work in 50 days, then in how many days both can finish the work together?