🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Karen can finish a work in 20 days. Lisa can finish the same work in 21 days while Nancy can finish the work in 22 days. How long will it take to finish it if they work together?


Correct Answer  6 654/661 days or 6.989 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Karen = 20 days

And, the number of days required to finish the same work by Lisa = 21 days

And, the number of days required to finish the same work by Nancy = 22 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 20 days the work is done by Karen = 1

∴ The work done by Karen in 1 day = 1/20

Similarly,

∵ In 21 days the work is done by Lisa = 1

∴ The work done by Lisa in 1 day = 1/21

Similarly,

∵ In 22 days the work is done by Nancy = 1

∴ The work done by Nancy in 1 day = 1/22 part

Now, the work done by Karen, Lisa, and Nancy together in 1 day

= Karen's 1 day work + Lisa's 1 day work + Nancy's 1 day work

= 1/20 + 1/21 + 1/22

= 231 + 220 + 210/4620

= 661/4620 part of work

This means in 1 day, 661/4620 part of work is done by Karen, Lisa and Nancy working together.

Now, the number of days required to finish 661/4620 part of work by Karen, Lisa, and Nancy working together = 1

∴ the number of days required to finish the whole work (1 work) by Karen + Lisa + Nancy together

= 1/661/4620

= 1 × 4620/661 = 4620/661 days

= 6 654/661 days = or 6.989 days

Thus, Karen, Lisa, and Nancy working together will finish the total work (1 work) in 6 654/661 days = or 6.989 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Karen = 20 days

And the number of days required to finish the same work by Lisa = 21 days

And the number of days required to finish the work by Nancy = 22 days

Thus, the number of days required to finish the work by Karen, Lisa, and Nancy together = ?

Here a = 20 days

And, b = 21 days

And, c = 22 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Karen, Lisa, and Nancy working together

= 20 × 21 × 22/20 × 21 + 20 × 22 + 21 × 22 days

= 9240/420 + 440 + 462 days

= 9240/1322 days

= 9240/1322 days

= 9240 ÷ 2/1322 ÷ 2 = 4620/661 days

= 6 654/661 days or 6.989

Thus, Karen, Lisa, and Nancy together will finish the work in 6 654/661 days or 6.989 days Answer


Similar Questions

(1) If A can do a piece of work in 2 days, B can do the same piece of work in 3 days, while C alone can do the same work in 4 days. Find the number of days to finish the work when they all will work together.

(2) If Benjamin can finish the work in 85 days and Gabriel can finish the same work in 90 days, then in how many days both can finish the work together?

(3) Michael can finish a work in 7 days. David can finish the same work in 8 days while William can finish the work in 9 days. How long will it take to finish it if they work together?

(4) If Donald can finish the work in 32 days and Nicholas can finish the same work in 35 days, then in how many days both can finish the work together?

(5) Amanda can finish a work in 48 days. Melissa can finish the same work in 53 days while Deborah can finish the work in 58 days. How long will it take to finish it if they work together?

(6) If Dorothy can finish the work in 50 days and Jack can finish the same work in 55 days, then in how many days both can finish the work together?

(7) Matthew can finish a work in 25 days. Anthony can finish the same work in 26 days while Mark can finish the work in 27 days. How long will it take to finish it if they work together?

(8) If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?

(9) If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?

(10) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?