🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?


Correct Answer  9 765/2351 days or 9.325 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Anthony = 27 days

And, the number of days required to finish the same work by Mark = 28 days

And, the number of days required to finish the same work by Donald = 29 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 27 days the work is done by Anthony = 1

∴ The work done by Anthony in 1 day = 1/27

Similarly,

∵ In 28 days the work is done by Mark = 1

∴ The work done by Mark in 1 day = 1/28

Similarly,

∵ In 29 days the work is done by Donald = 1

∴ The work done by Donald in 1 day = 1/29 part

Now, the work done by Anthony, Mark, and Donald together in 1 day

= Anthony's 1 day work + Mark's 1 day work + Donald's 1 day work

= 1/27 + 1/28 + 1/29

= 812 + 783 + 756/21924

= 2351/21924 part of work

This means in 1 day, 2351/21924 part of work is done by Anthony, Mark and Donald working together.

Now, the number of days required to finish 2351/21924 part of work by Anthony, Mark, and Donald working together = 1

∴ the number of days required to finish the whole work (1 work) by Anthony + Mark + Donald together

= 1/2351/21924

= 1 × 21924/2351 = 21924/2351 days

= 9 765/2351 days = or 9.325 days

Thus, Anthony, Mark, and Donald working together will finish the total work (1 work) in 9 765/2351 days = or 9.325 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Anthony = 27 days

And the number of days required to finish the same work by Mark = 28 days

And the number of days required to finish the work by Donald = 29 days

Thus, the number of days required to finish the work by Anthony, Mark, and Donald together = ?

Here a = 27 days

And, b = 28 days

And, c = 29 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Anthony, Mark, and Donald working together

= 27 × 28 × 29/27 × 28 + 27 × 29 + 28 × 29 days

= 21924/756 + 783 + 812 days

= 21924/2351 days

= 21924/2351 days

= 9 765/2351 days or 9.325

Thus, Anthony, Mark, and Donald together will finish the work in 9 765/2351 days or 9.325 days Answer


Similar Questions

(1) If Myra can finish the work in 15 days and Sophia can finish the same work in 20 days, then in how many days they both can finish the work working together?

(2) If Richard can finish the work in 14 days and Mark can finish the same work in 18 days, then in how many days both can finish the work together?

(3) If Catherine can finish the work in 100 days and Mason can finish the same work in 105 days, then in how many days both can finish the work together?

(4) If Daniel can finish the work in 27 days and Timothy can finish the same work in 32 days, then in how many days both can finish the work together?

(5) Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?

(6) Mary can finish a work in 6 days. Jennifer can finish the same work in 11 days while Linda can finish the work in 16 days. How long will it take to finish it if they work together?

(7) If Richard can finish the work in 14 days and Mark can finish the same work in 17 days, then in how many days both can finish the work together?

(8) If Melissa can finish the work in 49 days and Jerry can finish the same work in 52 days, then in how many days both can finish the work together?

(9) If John can finish the work in 6 days and Richard can finish the same work in 10 days, then in how many days both can finish the work together?

(10) If A can do a piece of work in 2 days, B can do the same piece of work in 3 days, while C alone can do the same work in 4 days. Find the number of days to finish the work when they all will work together.