🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Paul can finish a work in 35 days. Andrew can finish the same work in 36 days while Joshua can finish the work in 37 days. How long will it take to finish it if they work together?


Correct Answer  11 3863/3887 days or 11.994 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Paul = 35 days

And, the number of days required to finish the same work by Andrew = 36 days

And, the number of days required to finish the same work by Joshua = 37 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 35 days the work is done by Paul = 1

∴ The work done by Paul in 1 day = 1/35

Similarly,

∵ In 36 days the work is done by Andrew = 1

∴ The work done by Andrew in 1 day = 1/36

Similarly,

∵ In 37 days the work is done by Joshua = 1

∴ The work done by Joshua in 1 day = 1/37 part

Now, the work done by Paul, Andrew, and Joshua together in 1 day

= Paul's 1 day work + Andrew's 1 day work + Joshua's 1 day work

= 1/35 + 1/36 + 1/37

= 1332 + 1295 + 1260/46620

= 3887/46620 part of work

This means in 1 day, 3887/46620 part of work is done by Paul, Andrew and Joshua working together.

Now, the number of days required to finish 3887/46620 part of work by Paul, Andrew, and Joshua working together = 1

∴ the number of days required to finish the whole work (1 work) by Paul + Andrew + Joshua together

= 1/3887/46620

= 1 × 46620/3887 = 46620/3887 days

= 11 3863/3887 days = or 11.994 days

Thus, Paul, Andrew, and Joshua working together will finish the total work (1 work) in 11 3863/3887 days = or 11.994 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Paul = 35 days

And the number of days required to finish the same work by Andrew = 36 days

And the number of days required to finish the work by Joshua = 37 days

Thus, the number of days required to finish the work by Paul, Andrew, and Joshua together = ?

Here a = 35 days

And, b = 36 days

And, c = 37 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Paul, Andrew, and Joshua working together

= 35 × 36 × 37/35 × 36 + 35 × 37 + 36 × 37 days

= 46620/1260 + 1295 + 1332 days

= 46620/3887 days

= 46620/3887 days

= 11 3863/3887 days or 11.994

Thus, Paul, Andrew, and Joshua together will finish the work in 11 3863/3887 days or 11.994 days Answer


Similar Questions

(1) If Stephanie can finish the work in 56 days and Adam can finish the same work in 61 days, then in how many days both can finish the work together?

(2) If Patricia can finish the work in 5 days and William can finish the same work in 8 days, then in how many days both can finish the work together?

(3) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?

(4) If George can finish the work in 51 days and Dennis can finish the same work in 56 days, then in how many days both can finish the work together?

(5) If Nicole can finish the work in 82 days and Billy can finish the same work in 87 days, then in how many days both can finish the work together?

(6) If Annie can finish a work in 5 days and Bobby can finish the same work in 10 days, then in how many days they both can finish the work working together?

(7) Sharon can finish a work in 60 days. Cynthia can finish the same work in 65 days while Kathleen can finish the work in 70 days. How long will it take to finish it if they work together?

(8) If Ronald can finish the work in 55 days and Jose can finish the same work in 60 days, then in how many days both can finish the work together?

(9) If Mary can finish the work in 25 days and Michael can finish the same work in 41 days, then in how many days both can finish the work together?

(10) If Christine can finish the work in 90 days and Juan can finish the same work in 95 days, then in how many days both can finish the work together?