🏡 Home
    1. Time and Distance
    2. Time and Work
    3. Profit And Loss
    4. Average
    5. Percentage
    6. Simple Interest
    7. Questions based on ages
    1. Math
    2. Chemistry
    3. Chemistry Hindi
    4. Biology
    5. Exemplar Solution
    1. 11th physics
    2. 11th physics-hindi
    1. Science 10th (English)
    2. Science 10th (Hindi)
    3. Mathematics
    4. Math (Hindi)
    5. Social Science
    1. Science (English)
    2. 9th-Science (Hindi)
    1. 8th-Science (English)
    2. 8th-Science (Hindi)
    3. 8th-math (English)
    4. 8th-math (Hindi)
    1. 7th Math
    2. 7th Math(Hindi)
    1. Sixth Science
    2. 6th Science(hindi)
    1. Five Science
    1. Science (English)
    2. Science (Hindi)
    1. Std 10 science
    2. Std 4 science
    3. Std two EVS
    4. Std two Math
    5. MCQs Math
    6. एमoसीoक्यूo गणित
    7. Civil Service
    1. General Math (Hindi version)
    1. About Us
    2. Contact Us
10upon10.com

Time and Work
Math MCQs


Question :    Timothy can finish a work in 49 days. Ronald can finish the same work in 50 days while Edward can finish the work in 51 days. How long will it take to finish it if they work together?


Correct Answer  16 4966/7499 days or 16.662 days

Solution & Explanation

Solution

Given,

The number of days required to finish a piece of work by Timothy = 49 days

And, the number of days required to finish the same work by Ronald = 50 days

And, the number of days required to finish the same work by Edward = 51 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 49 days the work is done by Timothy = 1

∴ The work done by Timothy in 1 day = 1/49

Similarly,

∵ In 50 days the work is done by Ronald = 1

∴ The work done by Ronald in 1 day = 1/50

Similarly,

∵ In 51 days the work is done by Edward = 1

∴ The work done by Edward in 1 day = 1/51 part

Now, the work done by Timothy, Ronald, and Edward together in 1 day

= Timothy's 1 day work + Ronald's 1 day work + Edward's 1 day work

= 1/49 + 1/50 + 1/51

= 2550 + 2499 + 2450/124950

= 7499/124950 part of work

This means in 1 day, 7499/124950 part of work is done by Timothy, Ronald and Edward working together.

Now, the number of days required to finish 7499/124950 part of work by Timothy, Ronald, and Edward working together = 1

∴ the number of days required to finish the whole work (1 work) by Timothy + Ronald + Edward together

= 1/7499/124950

= 1 × 124950/7499 = 124950/7499 days

= 16 4966/7499 days = or 16.662 days

Thus, Timothy, Ronald, and Edward working together will finish the total work (1 work) in 16 4966/7499 days = or 16.662 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Timothy = 49 days

And the number of days required to finish the same work by Ronald = 50 days

And the number of days required to finish the work by Edward = 51 days

Thus, the number of days required to finish the work by Timothy, Ronald, and Edward together = ?

Here a = 49 days

And, b = 50 days

And, c = 51 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Timothy, Ronald, and Edward working together

= 49 × 50 × 51/49 × 50 + 49 × 51 + 50 × 51 days

= 124950/2450 + 2499 + 2550 days

= 124950/7499 days

= 124950/7499 days

= 16 4966/7499 days or 16.662

Thus, Timothy, Ronald, and Edward together will finish the work in 16 4966/7499 days or 16.662 days Answer


Similar Questions

(1) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?

(2) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(3) If John can finish the work in 6 days and Richard can finish the same work in 10 days, then in how many days both can finish the work together?

(4) If Jacob can finish the work in 65 days and Noah can finish the same work in 70 days, then in how many days both can finish the work together?

(5) Charles can finish a work in 23 days. Daniel can finish the same work in 28 days while Matthew can finish the work in 33 days. How long will it take to finish it if they work together?

(6) Emily can finish a work in 40 days. Michelle can finish the same work in 45 days while Carol can finish the work in 50 days. How long will it take to finish it if they work together?

(7) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 32 days, then in how many days both can finish the work together?

(8) If Mary can finish the work in 25 days and Michael can finish the same work in 41 days, then in how many days both can finish the work together?

(9) Dorothy can finish a work in 50 days. Deborah can finish the same work in 55 days while Stephanie can finish the work in 60 days. How long will it take to finish it if they work together?

(10) Thomas can finish a work in 17 days. Charles can finish the same work in 18 days while Christopher can finish the work in 19 days. How long will it take to finish it if they work together?