Time and Work
MCQs Math


Question:     If Jennifer can finish the work in 29 days and Joseph can finish the same work in 45 days, then in how many days both can finish the work together?


Correct Answer  17 47/74 days or 17.635 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Jennifer = 29 days

And, the number of days to finish the same work by Joseph = 45 days

Thus, the number of days to finish the work by Jennifer and Joseph together = ?

Here,

∵ In 29 days the work done by Jennifer = 1

∴ In 1 day, the work done by Jennifer = 1/29 part

Similarly,

∵ In 45 days the work done by Joseph = 1

∴ In 1 day, the work done by Joseph = 1/45 part

Now, in 1 day, the work done by Jennifer and Joseph together

= In 1 day work done by Jennifer + In 1 day the work done by Joseph

= 1/29 + 1/45

= 45 + 29/1305

= 74/1305 part of work

This means in 1 day, 74/1305 part of work is done by Jennifer and Joseph working together.

Now, the number of days required to finish 74/1305 part of work by Jennifer + Joseph working together = 1

∴ the number of days required to finish 1 work by Jennifer + Joseph together

= 1/74/1305

= 1 × 1305/74 = 1305/74 days

= 17 47/74 days = or 17.635 days

Thus, Jennifer and Joseph working together will finish the work in 17 47/74 days = or 17.635 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Jennifer = 29 days

And the number of days required to finish the same work by Joseph = 45 days

Thus, the number of days required to finish the work Jennifer and Joseph working together = ?

Here a = 29 days

And, b = 45 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Jennifer and Joseph working together

= 29 × 45/29 + 45 days

= 1305/74 days

= 17 47/74 days or 17.635

Thus, Jennifer and Joseph together will finish the work in 17 47/74 days or 17.635 days Answer


Similar Questions

(1) If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?

(2) If David can finish the work in 32 days and Christopher can finish the same work in 48 days, then in how many days both can finish the work together?

(3) Raymond can finish a work in 97 days. Dennis can finish the same work in 102 days while Jerry can finish the work in 107 days. How long will it take to finish it if they work together?

(4) Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?

(5) Donald can finish a work in 31 days. Steven can finish the same work in 32 days while Paul can finish the work in 33 days. How long will it take to finish it if they work together?

(6) If Pamela can finish the work in 78 days and Dylan can finish the same work in 83 days, then in how many days both can finish the work together?

(7) If Lisa can finish the work in 26 days and George can finish the same work in 31 days, then in how many days both can finish the work together?

(8) If Deborah can finish the work in 54 days and Aaron can finish the same work in 59 days, then in how many days both can finish the work together?

(9) Kevin can finish a work in 43 days. Brian can finish the same work in 44 days while George can finish the work in 45 days. How long will it take to finish it if they work together?

(10) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©