Time and Work
MCQs Math


Question:     If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?


Correct Answer  2 2/3 days or 2.667 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Robert = 4 days

And, the number of days to finish the same work by David = 8 days

Thus, the number of days to finish the work by Robert and David together = ?

Here,

∵ In 4 days the work done by Robert = 1

∴ In 1 day, the work done by Robert = 1/4 part

Similarly,

∵ In 8 days the work done by David = 1

∴ In 1 day, the work done by David = 1/8 part

Now, in 1 day, the work done by Robert and David together

= In 1 day work done by Robert + In 1 day the work done by David

= 1/4 + 1/8

= 2 + 1/8

= 3/8 part of work

This means in 1 day, 3/8 part of work is done by Robert and David working together.

Now, the number of days required to finish 3/8 part of work by Robert + David working together = 1

∴ the number of days required to finish 1 work by Robert + David together

= 1/3/8

= 1 × 8/3 = 8/3 days

= 2 2/3 days = or 2.667 days

Thus, Robert and David working together will finish the work in 2 2/3 days = or 2.667 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Robert = 4 days

And the number of days required to finish the same work by David = 8 days

Thus, the number of days required to finish the work Robert and David working together = ?

Here a = 4 days

And, b = 8 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Robert and David working together

= 4 × 8/4 + 8 days

= 32/12 days

= 32 ÷ 4/12 ÷ 4 = 8/3 days

= 2 2/3 days or 2.667

Thus, Robert and David together will finish the work in 2 2/3 days or 2.667 days Answer


Similar Questions

(1) Nicole can finish a work in 82 days. Samantha can finish the same work in 87 days while Katherine can finish the work in 92 days. How long will it take to finish it if they work together?

(2) If Cynthia can finish the work in 64 days and Walter can finish the same work in 69 days, then in how many days both can finish the work together?

(3) If Margaret can finish the work in 29 days and Ryan can finish the same work in 33 days, then in how many days both can finish the work together?

(4) If Barbara can finish the work in 16 days and Anthony can finish the same work in 21 days, then in how many days both can finish the work together?

(5) If Emily can finish the work in 37 days and Justin can finish the same work in 41 days, then in how many days both can finish the work together?

(6) Samuel can finish a work in 87 days. Alexander can finish the same work in 92 days while Frank can finish the work in 97 days. How long will it take to finish it if they work together?

(7) If Thomas can finish the work in 21 days and Andrew can finish the same work in 26 days, then in how many days both can finish the work together?

(8) If Sandra can finish the work in 31 days and Gary can finish the same work in 34 days, then in how many days both can finish the work together?

(9) Scott can finish a work in 81 days. Benjamin can finish the same work in 86 days while Samuel can finish the work in 91 days. How long will it take to finish it if they work together?

(10) If Emma can finish the work in 80 days and Jordan can finish the same work in 85 days, then in how many days both can finish the work together?