Time and Work
MCQs Math


Question:     If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?


Correct Answer  5 7/22 days or 5.318 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Linda = 9 days

And, the number of days to finish the same work by Charles = 13 days

Thus, the number of days to finish the work by Linda and Charles together = ?

Here,

∵ In 9 days the work done by Linda = 1

∴ In 1 day, the work done by Linda = 1/9 part

Similarly,

∵ In 13 days the work done by Charles = 1

∴ In 1 day, the work done by Charles = 1/13 part

Now, in 1 day, the work done by Linda and Charles together

= In 1 day work done by Linda + In 1 day the work done by Charles

= 1/9 + 1/13

= 13 + 9/117

= 22/117 part of work

This means in 1 day, 22/117 part of work is done by Linda and Charles working together.

Now, the number of days required to finish 22/117 part of work by Linda + Charles working together = 1

∴ the number of days required to finish 1 work by Linda + Charles together

= 1/22/117

= 1 × 117/22 = 117/22 days

= 5 7/22 days = or 5.318 days

Thus, Linda and Charles working together will finish the work in 5 7/22 days = or 5.318 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Linda = 9 days

And the number of days required to finish the same work by Charles = 13 days

Thus, the number of days required to finish the work Linda and Charles working together = ?

Here a = 9 days

And, b = 13 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Linda and Charles working together

= 9 × 13/9 + 13 days

= 117/22 days

= 5 7/22 days or 5.318

Thus, Linda and Charles together will finish the work in 5 7/22 days or 5.318 days Answer


Similar Questions

(1) If Christopher can finish the work in 22 days and Brian can finish the same work in 26 days, then in how many days both can finish the work together?

(2) Jessica can finish a work in 20 days. Karen can finish the same work in 25 days while Lisa can finish the work in 30 days. How long will it take to finish it if they work together?

(3) If Thomas can finish the work in 18 days and Andrew can finish the same work in 21 days, then in how many days both can finish the work together?

(4) Steven can finish a work in 33 days. Paul can finish the same work in 34 days while Andrew can finish the work in 35 days. How long will it take to finish it if they work together?

(5) If Sandra can finish the work in 31 days and Gary can finish the same work in 34 days, then in how many days both can finish the work together?

(6) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(7) Jack can finish a work in 99 days. Jerry can finish the same work in 104 days while Tyler can finish the work in 109 days. How long will it take to finish it if they work together?

(8) Kimberly can finish a work in 38 days. Donna can finish the same work in 43 days while Michelle can finish the work in 48 days. How long will it take to finish it if they work together?

(9) Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?

(10) Scott can finish a work in 81 days. Benjamin can finish the same work in 86 days while Samuel can finish the work in 91 days. How long will it take to finish it if they work together?