Time and Work
MCQs Math


Question:     If William can finish the work in 12 days and Matthew can finish the same work in 16 days, then in how many days both can finish the work together?


Correct Answer  6 6/7 days or 6.857 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by William = 12 days

And, the number of days to finish the same work by Matthew = 16 days

Thus, the number of days to finish the work by William and Matthew together = ?

Here,

∵ In 12 days the work done by William = 1

∴ In 1 day, the work done by William = 1/12 part

Similarly,

∵ In 16 days the work done by Matthew = 1

∴ In 1 day, the work done by Matthew = 1/16 part

Now, in 1 day, the work done by William and Matthew together

= In 1 day work done by William + In 1 day the work done by Matthew

= 1/12 + 1/16

= 4 + 3/48

= 7/48 part of work

This means in 1 day, 7/48 part of work is done by William and Matthew working together.

Now, the number of days required to finish 7/48 part of work by William + Matthew working together = 1

∴ the number of days required to finish 1 work by William + Matthew together

= 1/7/48

= 1 × 48/7 = 48/7 days

= 6 6/7 days = or 6.857 days

Thus, William and Matthew working together will finish the work in 6 6/7 days = or 6.857 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by William = 12 days

And the number of days required to finish the same work by Matthew = 16 days

Thus, the number of days required to finish the work William and Matthew working together = ?

Here a = 12 days

And, b = 16 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when William and Matthew working together

= 12 × 16/12 + 16 days

= 192/28 days

= 192 ÷ 4/28 ÷ 4 = 48/7 days

= 6 6/7 days or 6.857

Thus, William and Matthew together will finish the work in 6 6/7 days or 6.857 days Answer


Similar Questions

(1) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?

(2) If Justin can finish the work in 79 days and Jesse can finish the same work in 84 days, then in how many days both can finish the work together?

(3) If Donna can finish the work in 42 days and Brandon can finish the same work in 47 days, then in how many days both can finish the work together?

(4) Jason can finish a work in 59 days. Ryan can finish the same work in 64 days while Jacob can finish the work in 69 days. How long will it take to finish it if they work together?

(5) If Matthew can finish the work in 26 days and Edward can finish the same work in 29 days, then in how many days both can finish the work together?

(6) If Nancy can finish the work in 28 days and Ronald can finish the same work in 33 days, then in how many days both can finish the work together?

(7) If Matthew can finish the work in 29 days and Edward can finish the same work in 34 days, then in how many days both can finish the work together?

(8) Joseph can finish a work in 19 days. Charles can finish the same work in 24 days while Christopher can finish the work in 29 days. How long will it take to finish it if they work together?

(9) Sharon can finish a work in 60 days. Cynthia can finish the same work in 65 days while Kathleen can finish the work in 70 days. How long will it take to finish it if they work together?

(10) Sarah can finish a work in 22 days. Lisa can finish the same work in 27 days while Nancy can finish the work in 32 days. How long will it take to finish it if they work together?