Time and Work
MCQs Math


Question:     If Richard can finish the work in 14 days and Mark can finish the same work in 18 days, then in how many days both can finish the work together?


Correct Answer  7 7/8 days or 7.875 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Richard = 14 days

And, the number of days to finish the same work by Mark = 18 days

Thus, the number of days to finish the work by Richard and Mark together = ?

Here,

∵ In 14 days the work done by Richard = 1

∴ In 1 day, the work done by Richard = 1/14 part

Similarly,

∵ In 18 days the work done by Mark = 1

∴ In 1 day, the work done by Mark = 1/18 part

Now, in 1 day, the work done by Richard and Mark together

= In 1 day work done by Richard + In 1 day the work done by Mark

= 1/14 + 1/18

= 9 + 7/126

= 16/126 part of work

= 16 ÷ 2/126 ÷ 2 part of work

= 8/63 part of work

This means, in 1 day, 8/63 part of the work is done by Richard and Mark together.

Now, the number of days required to finish 8/63 part of work by Richard + Mark working together = 1

∴ the number of days required to finish 1 work by Richard + Mark together

= 1/8/63

= 1 × 63/8 = 63/8 days

= 7 7/8 days = or 7.875 days

Thus, Richard and Mark working together will finish the work in 7 7/8 days = or 7.875 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Richard = 14 days

And the number of days required to finish the same work by Mark = 18 days

Thus, the number of days required to finish the work Richard and Mark working together = ?

Here a = 14 days

And, b = 18 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Richard and Mark working together

= 14 × 18/14 + 18 days

= 252/32 days

= 252 ÷ 4/32 ÷ 4 = 63/8 days

= 7 7/8 days or 7.875

Thus, Richard and Mark together will finish the work in 7 7/8 days or 7.875 days Answer


Similar Questions

(1) Michael can finish a work in 11 days. William can finish the same work in 16 days while Richard can finish the work in 21 days. How long will it take to finish it if they work together?

(2) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 45 days, then in how many days both can finish the work together?

(3) If Michelle can finish the work in 44 days and Samuel can finish the same work in 49 days, then in how many days both can finish the work together?

(4) If Rachel can finish the work in 94 days and Roy can finish the same work in 99 days, then in how many days both can finish the work together?

(5) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 11 days, then in how many days both can finish the work together?

(6) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 44 days, then in how many days both can finish the work together?

(7) If Rebecca can finish the work in 58 days and Henry can finish the same work in 63 days, then in how many days both can finish the work together?

(8) Kevin can finish a work in 47 days. George can finish the same work in 52 days while Timothy can finish the work in 57 days. How long will it take to finish it if they work together?

(9) Margaret can finish a work in 32 days. Ashley can finish the same work in 37 days while Kimberly can finish the work in 42 days. How long will it take to finish it if they work together?

(10) Jennifer can finish a work in 10 days. Elizabeth can finish the same work in 15 days while Barbara can finish the work in 20 days. How long will it take to finish it if they work together?