Question:     If Nancy can finish the work in 25 days and Ronald can finish the same work in 29 days, then in how many days both can finish the work together?


Correct Answer  13 23/54 days or 13.426 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Nancy = 25 days

And, the number of days to finish the same work by Ronald = 29 days

Thus, the number of days to finish the work by Nancy and Ronald together = ?

Here,

∵ In 25 days the work done by Nancy = 1

∴ In 1 day, the work done by Nancy = 1/25 part

Similarly,

∵ In 29 days the work done by Ronald = 1

∴ In 1 day, the work done by Ronald = 1/29 part

Now, in 1 day, the work done by Nancy and Ronald together

= In 1 day work done by Nancy + In 1 day the work done by Ronald

= 1/25 + 1/29

= 29 + 25/725

= 54/725 part of work

This means in 1 day, 54/725 part of work is done by Nancy and Ronald working together.

Now, the number of days required to finish 54/725 part of work by Nancy + Ronald working together = 1

∴ the number of days required to finish 1 work by Nancy + Ronald together

= 1/54/725

= 1 × 725/54 = 725/54 days

= 13 23/54 days = or 13.426 days

Thus, Nancy and Ronald working together will finish the work in 13 23/54 days = or 13.426 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Nancy = 25 days

And the number of days required to finish the same work by Ronald = 29 days

Thus, the number of days required to finish the work Nancy and Ronald working together = ?

Here a = 25 days

And, b = 29 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Nancy and Ronald working together

= 25 × 29/25 + 29 days

= 725/54 days

= 13 23/54 days or 13.426

Thus, Nancy and Ronald together will finish the work in 13 23/54 days or 13.426 days Answer


Similar Questions

(1) If Amanda can finish the work in 45 days and Patrick can finish the same work in 48 days, then in how many days both can finish the work together?

(2) Christopher can finish a work in 21 days. Daniel can finish the same work in 22 days while Matthew can finish the work in 23 days. How long will it take to finish it if they work together?

(3) Jeffrey can finish a work in 61 days. Jacob can finish the same work in 66 days while Gary can finish the work in 71 days. How long will it take to finish it if they work together?

(4) Laura can finish a work in 62 days. Kathleen can finish the same work in 67 days while Amy can finish the work in 72 days. How long will it take to finish it if they work together?

(5) If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?

(6) Ashley can finish a work in 32 days. Kimberly can finish the same work in 33 days while Emily can finish the work in 34 days. How long will it take to finish it if they work together?

(7) Jennifer can finish a work in 10 days. Elizabeth can finish the same work in 15 days while Barbara can finish the work in 20 days. How long will it take to finish it if they work together?

(8) If Emma can finish the work in 80 days and Jordan can finish the same work in 85 days, then in how many days both can finish the work together?

(9) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?

(10) Dorothy can finish a work in 46 days. Melissa can finish the same work in 47 days while Deborah can finish the work in 48 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©