Time and Work
MCQs Math


Question:     If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?


Correct Answer  15 15/16 days or 15.938 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Mark = 30 days

And, the number of days to finish the same work by Jacob = 34 days

Thus, the number of days to finish the work by Mark and Jacob together = ?

Here,

∵ In 30 days the work done by Mark = 1

∴ In 1 day, the work done by Mark = 1/30 part

Similarly,

∵ In 34 days the work done by Jacob = 1

∴ In 1 day, the work done by Jacob = 1/34 part

Now, in 1 day, the work done by Mark and Jacob together

= In 1 day work done by Mark + In 1 day the work done by Jacob

= 1/30 + 1/34

= 17 + 15/510

= 32/510 part of work

= 32 ÷ 2/510 ÷ 2 part of work

= 16/255 part of work

This means, in 1 day, 16/255 part of the work is done by Mark and Jacob together.

Now, the number of days required to finish 16/255 part of work by Mark + Jacob working together = 1

∴ the number of days required to finish 1 work by Mark + Jacob together

= 1/16/255

= 1 × 255/16 = 255/16 days

= 15 15/16 days = or 15.938 days

Thus, Mark and Jacob working together will finish the work in 15 15/16 days = or 15.938 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Mark = 30 days

And the number of days required to finish the same work by Jacob = 34 days

Thus, the number of days required to finish the work Mark and Jacob working together = ?

Here a = 30 days

And, b = 34 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Mark and Jacob working together

= 30 × 34/30 + 34 days

= 1020/64 days

= 1020 ÷ 4/64 ÷ 4 = 255/16 days

= 15 15/16 days or 15.938

Thus, Mark and Jacob together will finish the work in 15 15/16 days or 15.938 days Answer


Similar Questions

(1) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 38 days, then in how many days both can finish the work together?

(2) Mary can finish a work in 6 days. Jennifer can finish the same work in 11 days while Linda can finish the work in 16 days. How long will it take to finish it if they work together?

(3) Joseph can finish a work in 19 days. Charles can finish the same work in 24 days while Christopher can finish the work in 29 days. How long will it take to finish it if they work together?

(4) If Carolyn can finish the work in 96 days and Ralph can finish the same work in 101 days, then in how many days both can finish the work together?

(5) If John can finish the work in 6 days and Richard can finish the same work in 9 days, then in how many days both can finish the work together?

(6) Rachel can finish a work in 94 days. Janet can finish the same work in 99 days while Catherine can finish the work in 104 days. How long will it take to finish it if they work together?

(7) Kenneth can finish a work in 41 days. Kevin can finish the same work in 42 days while Brian can finish the work in 43 days. How long will it take to finish it if they work together?

(8) If Eric can finish the work in 71 days and Gerald can finish the same work in 76 days, then in how many days both can finish the work together?

(9) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(10) If Larry can finish the work in 77 days and Lawrence can finish the same work in 82 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©