Time and Work
MCQs Math


Question:     If Ashley can finish the work in 33 days and Eric can finish the same work in 37 days, then in how many days both can finish the work together?


Correct Answer  17 31/70 days or 17.443 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Ashley = 33 days

And, the number of days to finish the same work by Eric = 37 days

Thus, the number of days to finish the work by Ashley and Eric together = ?

Here,

∵ In 33 days the work done by Ashley = 1

∴ In 1 day, the work done by Ashley = 1/33 part

Similarly,

∵ In 37 days the work done by Eric = 1

∴ In 1 day, the work done by Eric = 1/37 part

Now, in 1 day, the work done by Ashley and Eric together

= In 1 day work done by Ashley + In 1 day the work done by Eric

= 1/33 + 1/37

= 37 + 33/1221

= 70/1221 part of work

This means in 1 day, 70/1221 part of work is done by Ashley and Eric working together.

Now, the number of days required to finish 70/1221 part of work by Ashley + Eric working together = 1

∴ the number of days required to finish 1 work by Ashley + Eric together

= 1/70/1221

= 1 × 1221/70 = 1221/70 days

= 17 31/70 days = or 17.443 days

Thus, Ashley and Eric working together will finish the work in 17 31/70 days = or 17.443 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Ashley = 33 days

And the number of days required to finish the same work by Eric = 37 days

Thus, the number of days required to finish the work Ashley and Eric working together = ?

Here a = 33 days

And, b = 37 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Ashley and Eric working together

= 33 × 37/33 + 37 days

= 1221/70 days

= 17 31/70 days or 17.443

Thus, Ashley and Eric together will finish the work in 17 31/70 days or 17.443 days Answer


Similar Questions

(1) If Carol can finish the work in 43 days and Alexander can finish the same work in 47 days, then in how many days both can finish the work together?

(2) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(3) If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?

(4) Betty can finish a work in 26 days. Margaret can finish the same work in 27 days while Sandra can finish the work in 28 days. How long will it take to finish it if they work together?

(5) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(6) Daniel can finish a work in 27 days. Anthony can finish the same work in 32 days while Mark can finish the work in 37 days. How long will it take to finish it if they work together?

(7) If Joseph can finish the work in 19 days and Steven can finish the same work in 24 days, then in how many days both can finish the work together?

(8) If Amanda can finish the work in 48 days and Patrick can finish the same work in 53 days, then in how many days both can finish the work together?

(9) If Mary can finish the work in 25 days and Michael can finish the same work in 41 days, then in how many days both can finish the work together?

(10) Thomas can finish a work in 21 days. Christopher can finish the same work in 26 days while Daniel can finish the work in 31 days. How long will it take to finish it if they work together?