Time and Work
MCQs Math


Question:     If Amanda can finish the work in 45 days and Patrick can finish the same work in 49 days, then in how many days both can finish the work together?


Correct Answer  23 43/94 days or 23.457 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Amanda = 45 days

And, the number of days to finish the same work by Patrick = 49 days

Thus, the number of days to finish the work by Amanda and Patrick together = ?

Here,

∵ In 45 days the work done by Amanda = 1

∴ In 1 day, the work done by Amanda = 1/45 part

Similarly,

∵ In 49 days the work done by Patrick = 1

∴ In 1 day, the work done by Patrick = 1/49 part

Now, in 1 day, the work done by Amanda and Patrick together

= In 1 day work done by Amanda + In 1 day the work done by Patrick

= 1/45 + 1/49

= 49 + 45/2205

= 94/2205 part of work

This means in 1 day, 94/2205 part of work is done by Amanda and Patrick working together.

Now, the number of days required to finish 94/2205 part of work by Amanda + Patrick working together = 1

∴ the number of days required to finish 1 work by Amanda + Patrick together

= 1/94/2205

= 1 × 2205/94 = 2205/94 days

= 23 43/94 days = or 23.457 days

Thus, Amanda and Patrick working together will finish the work in 23 43/94 days = or 23.457 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Amanda = 45 days

And the number of days required to finish the same work by Patrick = 49 days

Thus, the number of days required to finish the work Amanda and Patrick working together = ?

Here a = 45 days

And, b = 49 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Amanda and Patrick working together

= 45 × 49/45 + 49 days

= 2205/94 days

= 23 43/94 days or 23.457

Thus, Amanda and Patrick together will finish the work in 23 43/94 days or 23.457 days Answer


Similar Questions

(1) If Sandra can finish the work in 31 days and Gary can finish the same work in 34 days, then in how many days both can finish the work together?

(2) Paul can finish a work in 35 days. Andrew can finish the same work in 36 days while Joshua can finish the work in 37 days. How long will it take to finish it if they work together?

(3) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 32 days, then in how many days both can finish the work together?

(4) Andrew can finish a work in 37 days. Joshua can finish the same work in 38 days while Kenneth can finish the work in 39 days. How long will it take to finish it if they work together?

(5) If Matthew can finish the work in 29 days and Edward can finish the same work in 34 days, then in how many days both can finish the work together?

(6) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?

(7) If Helen can finish the work in 84 days and Bruce can finish the same work in 89 days, then in how many days both can finish the work together?

(8) Amy can finish a work in 68 days. Shirley can finish the same work in 73 days while Anna can finish the work in 78 days. How long will it take to finish it if they work together?

(9) If William can finish the work in 34 days and Matthew can finish the same work in 50 days, then in how many days both can finish the work together?

(10) If Janet can finish the work in 98 days and Russell can finish the same work in 103 days, then in how many days both can finish the work together?