Time and Work
MCQs Math


Question:     If John can finish the work in 6 days and Richard can finish the same work in 9 days, then in how many days both can finish the work together?


Correct Answer  3 3/5 days or 3.6 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by John = 6 days

And, the number of days to finish the same work by Richard = 9 days

Thus, the number of days to finish the work by John and Richard together = ?

Here,

∵ In 6 days the work done by John = 1

∴ In 1 day, the work done by John = 1/6 part

Similarly,

∵ In 9 days the work done by Richard = 1

∴ In 1 day, the work done by Richard = 1/9 part

Now, in 1 day, the work done by John and Richard together

= In 1 day work done by John + In 1 day the work done by Richard

= 1/6 + 1/9

= 3 + 2/18

= 5/18 part of work

This means in 1 day, 5/18 part of work is done by John and Richard working together.

Now, the number of days required to finish 5/18 part of work by John + Richard working together = 1

∴ the number of days required to finish 1 work by John + Richard together

= 1/5/18

= 1 × 18/5 = 18/5 days

= 3 3/5 days = or 3.6 days

Thus, John and Richard working together will finish the work in 3 3/5 days = or 3.6 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by John = 6 days

And the number of days required to finish the same work by Richard = 9 days

Thus, the number of days required to finish the work John and Richard working together = ?

Here a = 6 days

And, b = 9 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when John and Richard working together

= 6 × 9/6 + 9 days

= 54/15 days

= 54 ÷ 3/15 ÷ 3 = 18/5 days

= 3 3/5 days or 3.6

Thus, John and Richard together will finish the work in 3 3/5 days or 3.6 days Answer


Similar Questions

(1) Charles can finish a work in 19 days. Christopher can finish the same work in 20 days while Daniel can finish the work in 21 days. How long will it take to finish it if they work together?

(2) If Elizabeth can finish the work in 14 days and Daniel can finish the same work in 19 days, then in how many days both can finish the work together?

(3) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 44 days, then in how many days both can finish the work together?

(4) If Susan can finish the work in 15 days and Donald can finish the same work in 18 days, then in how many days both can finish the work together?

(5) If Richard can finish the work in 14 days and Mark can finish the same work in 18 days, then in how many days both can finish the work together?

(6) Patrick can finish a work in 95 days. Jack can finish the same work in 100 days while Dennis can finish the work in 105 days. How long will it take to finish it if they work together?

(7) Brandon can finish a work in 83 days. Samuel can finish the same work in 88 days while Gregory can finish the work in 93 days. How long will it take to finish it if they work together?

(8) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 39 days, then in how many days both can finish the work together?

(9) If Joseph can finish the work in 16 days and Steven can finish the same work in 19 days, then in how many days both can finish the work together?

(10) Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?