Time and Work
MCQs Math


Question:     If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?


Correct Answer  4 12/19 days or 4.632 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Michael = 8 days

And, the number of days to finish the same work by Thomas = 11 days

Thus, the number of days to finish the work by Michael and Thomas together = ?

Here,

∵ In 8 days the work done by Michael = 1

∴ In 1 day, the work done by Michael = 1/8 part

Similarly,

∵ In 11 days the work done by Thomas = 1

∴ In 1 day, the work done by Thomas = 1/11 part

Now, in 1 day, the work done by Michael and Thomas together

= In 1 day work done by Michael + In 1 day the work done by Thomas

= 1/8 + 1/11

= 11 + 8/88

= 19/88 part of work

This means in 1 day, 19/88 part of work is done by Michael and Thomas working together.

Now, the number of days required to finish 19/88 part of work by Michael + Thomas working together = 1

∴ the number of days required to finish 1 work by Michael + Thomas together

= 1/19/88

= 1 × 88/19 = 88/19 days

= 4 12/19 days = or 4.632 days

Thus, Michael and Thomas working together will finish the work in 4 12/19 days = or 4.632 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Michael = 8 days

And the number of days required to finish the same work by Thomas = 11 days

Thus, the number of days required to finish the work Michael and Thomas working together = ?

Here a = 8 days

And, b = 11 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Michael and Thomas working together

= 8 × 11/8 + 11 days

= 88/19 days

= 4 12/19 days or 4.632

Thus, Michael and Thomas together will finish the work in 4 12/19 days or 4.632 days Answer


Similar Questions

(1) If Steven can finish the work in 34 days and Jonathan can finish the same work in 37 days, then in how many days both can finish the work together?

(2) Susan can finish a work in 18 days. Sarah can finish the same work in 23 days while Karen can finish the work in 28 days. How long will it take to finish it if they work together?

(3) If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?

(4) If Amanda can finish the work in 48 days and Patrick can finish the same work in 53 days, then in how many days both can finish the work together?

(5) If George can finish the work in 51 days and Dennis can finish the same work in 56 days, then in how many days both can finish the work together?

(6) Karen can finish a work in 20 days. Lisa can finish the same work in 21 days while Nancy can finish the work in 22 days. How long will it take to finish it if they work together?

(7) If Michelle can finish the work in 41 days and Samuel can finish the same work in 45 days, then in how many days both can finish the work together?

(8) Margaret can finish a work in 32 days. Ashley can finish the same work in 37 days while Kimberly can finish the work in 42 days. How long will it take to finish it if they work together?

(9) Timothy can finish a work in 49 days. Ronald can finish the same work in 50 days while Edward can finish the work in 51 days. How long will it take to finish it if they work together?

(10) If Emily can finish the work in 37 days and Justin can finish the same work in 40 days, then in how many days both can finish the work together?