Time and Work
MCQs Math


Question:     If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?


Correct Answer  4 12/19 days or 4.632 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Michael = 8 days

And, the number of days to finish the same work by Thomas = 11 days

Thus, the number of days to finish the work by Michael and Thomas together = ?

Here,

∵ In 8 days the work done by Michael = 1

∴ In 1 day, the work done by Michael = 1/8 part

Similarly,

∵ In 11 days the work done by Thomas = 1

∴ In 1 day, the work done by Thomas = 1/11 part

Now, in 1 day, the work done by Michael and Thomas together

= In 1 day work done by Michael + In 1 day the work done by Thomas

= 1/8 + 1/11

= 11 + 8/88

= 19/88 part of work

This means in 1 day, 19/88 part of work is done by Michael and Thomas working together.

Now, the number of days required to finish 19/88 part of work by Michael + Thomas working together = 1

∴ the number of days required to finish 1 work by Michael + Thomas together

= 1/19/88

= 1 × 88/19 = 88/19 days

= 4 12/19 days = or 4.632 days

Thus, Michael and Thomas working together will finish the work in 4 12/19 days = or 4.632 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Michael = 8 days

And the number of days required to finish the same work by Thomas = 11 days

Thus, the number of days required to finish the work Michael and Thomas working together = ?

Here a = 8 days

And, b = 11 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Michael and Thomas working together

= 8 × 11/8 + 11 days

= 88/19 days

= 4 12/19 days or 4.632

Thus, Michael and Thomas together will finish the work in 4 12/19 days or 4.632 days Answer


Similar Questions

(1) If Paul can finish the work in 36 days and Larry can finish the same work in 40 days, then in how many days both can finish the work together?

(2) If Mark can finish the work in 33 days and Jacob can finish the same work in 38 days, then in how many days both can finish the work together?

(3) Brenda can finish a work in 76 days. Emma can finish the same work in 81 days while Nicole can finish the work in 86 days. How long will it take to finish it if they work together?

(4) Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?

(5) If Jeffrey can finish the work in 61 days and Peter can finish the same work in 66 days, then in how many days both can finish the work together?

(6) If Stephen can finish the work in 75 days and Carl can finish the same work in 80 days, then in how many days both can finish the work together?

(7) Carolyn can finish a work in 96 days. Catherine can finish the same work in 101 days while Maria can finish the work in 106 days. How long will it take to finish it if they work together?

(8) If Patricia can finish the work in 5 days and William can finish the same work in 9 days, then in how many days both can finish the work together?

(9) If Dorothy can finish the work in 50 days and Jack can finish the same work in 55 days, then in how many days both can finish the work together?

(10) If Barbara can finish the work in 13 days and Anthony can finish the same work in 17 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©