Time and Work
MCQs Math


Question:     If David can finish the work in 10 days and Christopher can finish the same work in 13 days, then in how many days both can finish the work together?


Correct Answer  5 15/23 days or 5.652 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by David = 10 days

And, the number of days to finish the same work by Christopher = 13 days

Thus, the number of days to finish the work by David and Christopher together = ?

Here,

∵ In 10 days the work done by David = 1

∴ In 1 day, the work done by David = 1/10 part

Similarly,

∵ In 13 days the work done by Christopher = 1

∴ In 1 day, the work done by Christopher = 1/13 part

Now, in 1 day, the work done by David and Christopher together

= In 1 day work done by David + In 1 day the work done by Christopher

= 1/10 + 1/13

= 13 + 10/130

= 23/130 part of work

This means in 1 day, 23/130 part of work is done by David and Christopher working together.

Now, the number of days required to finish 23/130 part of work by David + Christopher working together = 1

∴ the number of days required to finish 1 work by David + Christopher together

= 1/23/130

= 1 × 130/23 = 130/23 days

= 5 15/23 days = or 5.652 days

Thus, David and Christopher working together will finish the work in 5 15/23 days = or 5.652 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by David = 10 days

And the number of days required to finish the same work by Christopher = 13 days

Thus, the number of days required to finish the work David and Christopher working together = ?

Here a = 10 days

And, b = 13 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when David and Christopher working together

= 10 × 13/10 + 13 days

= 130/23 days

= 5 15/23 days or 5.652

Thus, David and Christopher together will finish the work in 5 15/23 days or 5.652 days Answer


Similar Questions

(1) Amy can finish a work in 68 days. Shirley can finish the same work in 73 days while Anna can finish the work in 78 days. How long will it take to finish it if they work together?

(2) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?

(3) If Jennifer can finish the work in 29 days and Joseph can finish the same work in 45 days, then in how many days both can finish the work together?

(4) If Melissa can finish the work in 49 days and Jerry can finish the same work in 52 days, then in how many days both can finish the work together?

(5) If Nancy can finish the work in 28 days and Ronald can finish the same work in 33 days, then in how many days both can finish the work together?

(6) Mary can finish a work in 6 days. Jennifer can finish the same work in 11 days while Linda can finish the work in 16 days. How long will it take to finish it if they work together?

(7) If Donald can finish the work in 32 days and Nicholas can finish the same work in 35 days, then in how many days both can finish the work together?

(8) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?

(9) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?

(10) Kenneth can finish a work in 45 days. Brian can finish the same work in 50 days while George can finish the work in 55 days. How long will it take to finish it if they work together?