Time and Work
MCQs Math


Question:     If Robert can finish a work in 4 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?


Correct Answer  22/5 days or 2.4 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Robert = 4 days

And, the number of days to finish the same work by Bob = 6 days

Thus, the number of days to finish the work by Rober and Bob working together = ?

Here, ∵ In 4 days the work done by Robert = 1

∴ In 1 day, the work done by Robert = 1/4

Similarly, ∵ In 6 days the work done by Bob = 1

∴ In 1 day, the work done by Bob = 1/6

Now, in 1 day, the work done by Robert and Bob working together

= In 1 day work done by Robert + In 1 day the work done by Bob

= 1/4 + 1/6

= 3 + 2/12

= 5/12

This means in 1 day, 5/12 part of work is done by Robert and Bob working together.

Now, the number of days required to finish 5/12 work by Robert + Bob working together = 1

∴ the number of days required to finish 1 work by Rpbert + Bob working together

= 1/5/12

= 1 × 12/5 days = 2 2/5 days = 2.4 days

Thus, Robert and Bob working together will finish the work in 2 2/5 days or 2.4 days. Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in "a" days, and B can finish the same work in "b" days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days to finish the work by Robert = 4 days

And, the number of days to finish the same work by Bob = 6 days

Thus, the number of days to finish the work by Robert and Bob working together = ?

Here "a" = 4 days

And, "b" = 6 days

Thus, using formula a × b/a + b days

The number of days reqire to finish the work when Robert and Bob work together

= 4 × 6/4 + 6

= 24 12/10 5

= 12/5 = 2 2/5 days = 2.4 days

Thus, Robert and Bob working together will finish the work in 2 2/5 days or 2.4 days. Answer


Similar Questions

(1) Karen can finish a work in 24 days. Nancy can finish the same work in 29 days while Betty can finish the work in 34 days. How long will it take to finish it if they work together?

(2) If Donald can finish the work in 32 days and Nicholas can finish the same work in 36 days, then in how many days both can finish the work together?

(3) Sarah can finish a work in 22 days. Lisa can finish the same work in 27 days while Nancy can finish the work in 32 days. How long will it take to finish it if they work together?

(4) If Mark can finish the work in 30 days and Jacob can finish the same work in 33 days, then in how many days both can finish the work together?

(5) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 39 days, then in how many days both can finish the work together?

(6) Lisa can finish a work in 26 days. Betty can finish the same work in 31 days while Margaret can finish the work in 36 days. How long will it take to finish it if they work together?

(7) If Charles can finish the work in 20 days and Kenneth can finish the same work in 23 days, then in how many days both can finish the work together?

(8) Amy can finish a work in 68 days. Shirley can finish the same work in 73 days while Anna can finish the work in 78 days. How long will it take to finish it if they work together?

(9) If David can finish the work in 10 days and Christopher can finish the same work in 14 days, then in how many days both can finish the work together?

(10) If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©