Time and Work
MCQs Math


Question:     If Matthew can finish the work in 26 days and Edward can finish the same work in 29 days, then in how many days both can finish the work together?


Correct Answer  13 39/55 days or 13.709 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Matthew = 26 days

And, the number of days to finish the same work by Edward = 29 days

Thus, the number of days to finish the work by Matthew and Edward together = ?

Here,

∵ In 26 days the work done by Matthew = 1

∴ In 1 day, the work done by Matthew = 1/26 part

Similarly,

∵ In 29 days the work done by Edward = 1

∴ In 1 day, the work done by Edward = 1/29 part

Now, in 1 day, the work done by Matthew and Edward together

= In 1 day work done by Matthew + In 1 day the work done by Edward

= 1/26 + 1/29

= 29 + 26/754

= 55/754 part of work

This means in 1 day, 55/754 part of work is done by Matthew and Edward working together.

Now, the number of days required to finish 55/754 part of work by Matthew + Edward working together = 1

∴ the number of days required to finish 1 work by Matthew + Edward together

= 1/55/754

= 1 × 754/55 = 754/55 days

= 13 39/55 days = or 13.709 days

Thus, Matthew and Edward working together will finish the work in 13 39/55 days = or 13.709 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Matthew = 26 days

And the number of days required to finish the same work by Edward = 29 days

Thus, the number of days required to finish the work Matthew and Edward working together = ?

Here a = 26 days

And, b = 29 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Matthew and Edward working together

= 26 × 29/26 + 29 days

= 754/55 days

= 13 39/55 days or 13.709

Thus, Matthew and Edward together will finish the work in 13 39/55 days or 13.709 days Answer


Similar Questions

(1) Sandra can finish a work in 30 days. Ashley can finish the same work in 31 days while Kimberly can finish the work in 32 days. How long will it take to finish it if they work together?

(2) Patricia can finish a work in 8 days. Linda can finish the same work in 13 days while Elizabeth can finish the work in 18 days. How long will it take to finish it if they work together?

(3) If Samuel can finish the work in 87 days and Albert can finish the same work in 92 days, then in how many days both can finish the work together?

(4) If Sharon can finish the work in 60 days and Zachary can finish the same work in 65 days, then in how many days both can finish the work together?

(5) If Samantha can finish the work in 86 days and Logan can finish the same work in 91 days, then in how many days both can finish the work together?

(6) Donna can finish a work in 42 days. Carol can finish the same work in 47 days while Amanda can finish the work in 52 days. How long will it take to finish it if they work together?

(7) If David can finish the work in 10 days and Christopher can finish the same work in 14 days, then in how many days both can finish the work together?

(8) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 45 days, then in how many days both can finish the work together?

(9) Catherine can finish a work in 100 days. Heather can finish the same work in 105 days while Diane can finish the work in 110 days. How long will it take to finish it if they work together?

(10) If Ashley can finish the work in 33 days and Eric can finish the same work in 37 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©