Time and Work
MCQs Math


Question:     If Kimberly can finish the work in 35 days and Stephen can finish the same work in 38 days, then in how many days both can finish the work together?


Correct Answer  18 16/73 days or 18.219 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Kimberly = 35 days

And, the number of days to finish the same work by Stephen = 38 days

Thus, the number of days to finish the work by Kimberly and Stephen together = ?

Here,

∵ In 35 days the work done by Kimberly = 1

∴ In 1 day, the work done by Kimberly = 1/35 part

Similarly,

∵ In 38 days the work done by Stephen = 1

∴ In 1 day, the work done by Stephen = 1/38 part

Now, in 1 day, the work done by Kimberly and Stephen together

= In 1 day work done by Kimberly + In 1 day the work done by Stephen

= 1/35 + 1/38

= 38 + 35/1330

= 73/1330 part of work

This means in 1 day, 73/1330 part of work is done by Kimberly and Stephen working together.

Now, the number of days required to finish 73/1330 part of work by Kimberly + Stephen working together = 1

∴ the number of days required to finish 1 work by Kimberly + Stephen together

= 1/73/1330

= 1 × 1330/73 = 1330/73 days

= 18 16/73 days = or 18.219 days

Thus, Kimberly and Stephen working together will finish the work in 18 16/73 days = or 18.219 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Kimberly = 35 days

And the number of days required to finish the same work by Stephen = 38 days

Thus, the number of days required to finish the work Kimberly and Stephen working together = ?

Here a = 35 days

And, b = 38 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Kimberly and Stephen working together

= 35 × 38/35 + 38 days

= 1330/73 days

= 18 16/73 days or 18.219

Thus, Kimberly and Stephen together will finish the work in 18 16/73 days or 18.219 days Answer


Similar Questions

(1) Nicole can finish a work in 82 days. Samantha can finish the same work in 87 days while Katherine can finish the work in 92 days. How long will it take to finish it if they work together?

(2) If Amanda can finish the work in 45 days and Patrick can finish the same work in 49 days, then in how many days both can finish the work together?

(3) Nicholas can finish a work in 69 days. Jonathan can finish the same work in 74 days while Stephen can finish the work in 79 days. How long will it take to finish it if they work together?

(4) If Sandra can finish the work in 34 days and Gary can finish the same work in 39 days, then in how many days both can finish the work together?

(5) If Sandra can finish the work in 31 days and Gary can finish the same work in 35 days, then in how many days both can finish the work together?

(6) If Nancy can finish the work in 25 days and Ronald can finish the same work in 28 days, then in how many days both can finish the work together?

(7) If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?

(8) If Brenda can finish the work in 76 days and Arthur can finish the same work in 81 days, then in how many days both can finish the work together?

(9) If Elizabeth can finish the work in 14 days and Daniel can finish the same work in 19 days, then in how many days both can finish the work together?

(10) If Susan can finish the work in 15 days and Donald can finish the same work in 18 days, then in how many days both can finish the work together?